The gantry crane installation work for the lifting capacity enhancement project at the No. 2 dock area of Shanghai Waigaoqiao Shipbuilding Co., Ltd. has been carried out on a full scale.
Once the project is completed and put into operation, it will further enhance the shipyard's ability to hoist and integrate large vessel blocks, better accommodate the construction needs of high-end ship types such as Very Large Crude Carriers (VLCC) and large container ships, and provide important equipment support for intelligent and efficient production at large docks.
The four major components being hoisted this time — the rigid leg, flexible leg, main girder, and upper trolley — are large in size and heavy in weight. The operation waters cover an area of 900 meters by 350 meters within the dock, requiring coordinated efforts among multiple vessels, which places considerable pressure on navigation safety assurance.
The Pudong Maritime Safety Administration intervened in advance and maintained full-process supervision, weaving a safety "protection net" from the water surface to the sky to ensure the safe and smooth completion of the hoisting operation.
The Pudong Maritime Safety Administration took the initiative to coordinate with the construction unit, thoroughly understanding the hoisting plan, component entry schedule, floating crane anchoring and positioning scheme, and operational procedures. It guided the improvement of navigation safety assurance measures, issued navigation notices in a timely manner, and informed passing vessels in advance of the operation time, waters, methods, and safety precautions.
At the same time, it urged operating vessels to display signal lights and shapes as required, maintain normal AIS operation, strengthen VHF channel watchkeeping and dynamic reporting, and strictly control the "admission gate" for operations.
During the operation, law enforcement personnel conducted remote monitoring of the lifting site. Relying on the CCTV system, they carried out remote supervision of the lifting site, gaining real-time awareness of component lifting posture, rigging stress conditions, floating crane anchoring and positioning, and surrounding vessel dynamics.
They urged the construction unit and the crane vessel to fulfill their primary responsibilities for production safety, strictly implementing requirements such as suspending operations when wind force exceeds level 6 or visibility falls below 1,000 meters, and avoiding peak traffic flows of upstream and downstream vessels during construction vessel positioning and hoisting operations, ensuring that all aspects of the tandem lifting operation remain safe and controllable.
During the hoisting period, maritime patrol boats were deployed to the operation waters in advance to implement on-site warning and escort duties, maintaining order throughout the tandem lifting operation, promptly guiding vessels entering and leaving the dock and those passing through, and strictly preventing unrelated vessels from straying into the construction area.
In the air, drones simultaneously conducted patrol inspections, providing an aerial overview of component transfer, floating crane positioning, and navigation order. Working in coordination with the AIS and CCTV monitoring of the "Smart Maritime" system, they formed a three-dimensional "land-sea-air" supervision network, achieving full dynamic awareness of the construction waters and early risk detection.
Next, the Pudong Maritime Safety Administration will continue to monitor large-component hoisting operations in its jurisdiction. Based on the cargo hoisting needs of different terminals, it will dynamically optimize safety supervision and service assurance measures, striving to create a safe, orderly, and unimpeded water traffic environment, and contributing to the economic development of the Shanghai Port region.