Unit 3 Main Works Begin at CGN Guangdong Taishan Nuclear Power Project

Deep News11-28 11:30

The first concrete pour for the nuclear island of Unit 3 at CGN's Guangdong Taishan Nuclear Power Project began at 10:18 on November 25, officially marking the start of construction on Phase II of the Taishan nuclear power project.

The pour took place at the nuclear island of Unit 3 at the CGN Guangdong Taishan Nuclear Power Project. The Taishan nuclear power project is located in Chixi Town, Taishan City, Jiangmen City, Guangdong Province, at the southwestern tip of the Guangdong-Hong Kong-Macao Greater Bay Area and close to the power load center of the Pearl River Delta.

The Unit 3 now under construction is part of Phase II of the Taishan nuclear power project, which received national approval on April 27, 2025. It adopts China's third-generation nuclear power technology "Hualong One," over which the country holds fully independent intellectual property rights. It is the fourth nuclear power unit CGN has started this year. Once completed, it will generate more than 9 billion kilowatt-hours of electricity annually, enough to meet the annual production and living electricity demand of about 1 million people.

The total concrete pouring volume for the nuclear island raft foundation of Unit 3 is about 8,823 cubic meters and is expected to last 55 hours. During the early preparation stage, the project team ensured high-quality progress at key milestones by introducing advanced construction technologies, carrying out technical innovation and optimizing processes. It built supporting automated production lines for stainless steel and steel structures, put intelligent equipment such as welding robots and safety monitoring sentinels into use to improve the processing quality of components and production efficiency, and innovatively implemented a modular management model featuring "prefabricated wall reinforcement and parallel foundation wall construction," effectively shortening the critical path schedule and eliminating the risk of missed dowel bars at the source.

It is learned that Phase II of the Taishan nuclear power project will use high-level water-collecting natural draft cooling towers, relying on the atmospheric heat sink to carry away the waste heat of the conventional island thermodynamic cycle, achieving circulating use of cooling water and reducing the impact of thermal discharge on marine ecology. While saving energy and reducing consumption and ensuring the safety of the cold source, it will provide strong protection for the marine environment and biodiversity.

It is understood that the Taishan nuclear power project plans six million-kilowatt-class nuclear power units to be built in three phases. The two units of Phase I were fully completed and put into operation on September 7, 2019. As an important project for Jiangmen to build a modern and vibrant new hometown of overseas Chinese and to build an energy base in the Greater Bay Area, Phase II will further enhance the region's clean energy supply capacity once it is put into operation.

Disclaimer: Investing carries risk. This is not financial advice. The above content should not be regarded as an offer, recommendation, or solicitation on acquiring or disposing of any financial products, any associated discussions, comments, or posts by author or other users should not be considered as such either. It is solely for general information purpose only, which does not consider your own investment objectives, financial situations or needs. TTM assumes no responsibility or warranty for the accuracy and completeness of the information, investors should do their own research and may seek professional advice before investing.