7 Yunnan Solar Projects Totaling 675MW Launch Investor Selection with Over 2.9 Billion Yuan in Investment

Deep News11-09

Yunnan has launched competitive selection processes for the investment entities of seven photovoltaic power projects, with a combined capacity of 675MW and total investment of approximately 2.902272 billion yuan.

The announcements cover the first batch of 2026 projects in Pu'er City, including the Chahe Village and Wenyu Village photovoltaic power generation projects, as well as the first batch of 2026 new energy projects in Jinghong City, which include the Manhedong Xinzhai photovoltaic project (Phase I), the Manhedong Xinzhai photovoltaic project (Phase II), the Manhena Group 2 photovoltaic project, the Mangolong Village photovoltaic project, and the Bala photovoltaic project.

For the Pu'er City projects, the construction timeline requires that projects generally be ready for operation within 8 months of commencement and achieve full-capacity grid connection within 1 year of commencement. Projects must commence construction within one year from the issuance date of the provincial development and construction plan, namely the Yunnan Provincial Development and Reform Commission and Yunnan Provincial Energy Administration Notice on Issuing the Yunnan Province 2026 First Batch New Energy Project Development and Construction Plan (Yun Neng Yuan Xin Neng [2026] No. 160).

The scope of negotiation covers all work including full fundraising for grid connection and operation, bidding management during construction, project construction management, grid connection, operation, and maintenance management. All costs and risks associated with project development, construction, and operation shall be fully borne by the project investor.

For the Jinghong City first batch of 2026 new energy projects, the Manhedong Xinzhai photovoltaic project (Phase I) has an installed capacity of 35,000 kilowatts with an estimated total investment of approximately 140.45 million yuan. Upon completion, it is expected to generate an average annual power output of approximately 57.43 million kilowatt-hours and an annual output value of approximately 14.35 million yuan.

The Manhedong Xinzhai photovoltaic project (Phase II) also has an installed capacity of 35,000 kilowatts with an estimated total investment of approximately 140.45 million yuan. Upon completion, it is expected to generate an average annual power output of approximately 57.43 million kilowatt-hours and an annual output value of approximately 14.35 million yuan.

The Manhena Group 2 photovoltaic project has an installed capacity of 20,000 kilowatts with an estimated total investment of approximately 80.272 million yuan. Upon completion, it is expected to generate an average annual power output of approximately 32.8362 million kilowatt-hours and an annual output value of approximately 9.0295 million yuan.

The Mangolong Village photovoltaic project has an installed capacity of 35,000 kilowatts with an estimated total investment of approximately 140.45 million yuan. Upon completion, it is expected to generate an average annual power output of approximately 57.43 million kilowatt-hours and an annual output value of approximately 14.35 million yuan.

Regarding the contract performance period, after signing the photovoltaic project investment and development cooperation agreement, the project owner must complete project filing within 1 month and commence construction within 2 months of completing the filing. The time required for processing pre-construction procedures such as forestry and land use, environmental protection and water conservation, and grid connection system approval may be excluded, with the exclusion period not exceeding 2 months. In principle, projects should be ready for operation within 6 months of commencement and achieve full-capacity grid connection within 1 year of commencement.

The bidding scope covers all work for which the social investor is responsible for the Jinghong City Development and Reform Bureau's Manhedong Xinzhai photovoltaic project (Phase I), Manhedong Xinzhai photovoltaic project (Phase II), Manhena Group 2 photovoltaic project, and Mangolong Village photovoltaic project, including full fundraising for development and grid connection, bidding management during construction, project construction management, grid connection, operation, and maintenance management. All costs and risks associated with project development, construction, and operation shall be fully borne by the project social investor.

Specific work content and requirements shall be subject to the actual entrustment by the tendering party, and the tendering party may adjust according to specific project conditions during implementation.

For the Jinghong City first batch of 2026 new energy projects, the Bala photovoltaic project has an installed capacity of 50,000 kilowatts with an estimated total investment of approximately 200.65 million yuan. Upon completion, it is expected to generate an average annual power output of approximately 82.05 million kilowatt-hours and an annual output value of approximately 20.51 million yuan.

Regarding the contract performance period, after signing the photovoltaic project investment and development cooperation agreement, the project owner must complete project filing within 1 month and commence construction within 2 months of completing the filing. The time required for processing pre-construction procedures such as forestry and land use, environmental protection and water conservation, and grid connection system approval may be excluded, with the exclusion period not exceeding 2 months. In principle, projects should be ready for operation within 6 months of commencement and achieve full-capacity grid connection within 1 year of commencement.

The bidding scope covers all work for which the social investor is responsible for the Jinghong City Development and Reform Bureau's Bala photovoltaic project, including full fundraising for development and grid connection, bidding management during construction, project construction management, grid connection, operation, and maintenance management. All costs and risks associated with project development, construction, and operation shall be fully borne by the project social investor.

The announcements are as follows:

Disclaimer: Investing carries risk. This is not financial advice. The above content should not be regarded as an offer, recommendation, or solicitation on acquiring or disposing of any financial products, any associated discussions, comments, or posts by author or other users should not be considered as such either. It is solely for general information purpose only, which does not consider your own investment objectives, financial situations or needs. TTM assumes no responsibility or warranty for the accuracy and completeness of the information, investors should do their own research and may seek professional advice before investing.