Tangshan in Hebei province has set up a joint city-county investigation team to conduct a full review of a sewage treatment plant that was built but never put into operation, according to a statement released on November 16 through the "Luannan Publicity" WeChat account.
The statement said the Tangshan municipal party committee and government, along with the Luannan county party committee and government, have attached great importance to media reports about the plant in Hu'gezhuang township that has remained idle since completion, and will handle the matter strictly in accordance with laws and regulations based on the investigation results.
The facility, built with more than 8 million yuan ($1.1 million) in government investment, has not been used for four years, according to a report in the People's Daily on November 16. A netizen had raised the issue on the "Leadership Message Board" of People.cn, noting that the plant in Hu'gezhuang township had never been activated since its completion, and that vegetables such as cabbage and corn were now being grown on its grounds, while the road surface above its pipeline network had caved in.
Following the tip, a reporter traveled to Luannan county on November 10 to investigate. At Hu'gezhuang township, the first sight was the black, foul-smelling water in the Hu'gezhuang No. 2 drainage channel, a street-level canal running through the township that serves flood control and drainage for several villages and also functions as an ecological waterway.
The channel was overgrown with weeds and piled with household garbage. The water was dark black with white foam on the surface and gave off a pungent stench. The polluted waterway stretches more than 3 kilometers north to south along the Gulin county road, flanked by a market town and farmland, with dozens of shops and hundreds of farming households nearby.
Walking south along the bank, the reporter saw four or five drainage outlets on the eastern side discharging sewage, with flies swarming around and food scraps, plastic foam, plastic bags and liquor bottles piled up near the outlets. Several villagers and shopkeepers interviewed expressed anger over the filthy and smelly channel.
"When we were children, we used to catch fish and shrimp in the water. The water quality was good. Later, factories and schools were built, and the river gradually became polluted. It has gotten worse over the years," an older villager said. A shopkeeper said: "Sewage flows all year round. In summer the stench is unbearable, and we can't even open our windows. Now that winter has come and it snowed a few days ago, the smell is a bit less today." The shopkeeper added that when someone accidentally fell into the water, the sludge stuck to their body and stains remained even after washing for a long time.
About 100 meters east of the channel, the reporter found the Hu'gezhuang township sewage treatment plant mentioned by the netizen. The plant covers a small area, and part of its western fence has collapsed. Its iron gate has no sign and is loosely tied with black rope, with no one guarding it. Inside, weeds have spread, cabbage and corn are grown in some spots, and agricultural plastic film covers others. A equipment room is locked, with no signs of any machinery operating.
A public notice board outside the equipment room states that Hu'gezhuang township, as a provincial-level characteristic town, was required by higher-level housing and construction authorities to complete a township-level sewage treatment facility. In September 2018, with county government approval, Luannan County Urban Construction Development Co., a subsidiary of the county housing and construction bureau, undertook the project with an estimated total investment of 8.18 million yuan.
The notice said the facility was mainly to collect domestic and production sewage from the Hu'gezhuang spinning park, a middle school, a high school, a health center and shops along the streets, benefiting more than 3,000 people, with a daily treatment capacity of 500 cubic meters. The pipeline network was laid along several roads totaling 3,062 meters, and the plant site, located at the southern end of the Hu'gezhuang market, covers about 2.3 mu (about 0.15 hectares).
"When construction started, we were very hopeful and happy," a nearby shopkeeper said, but after completion it was never used. Sewage from shops and villages was never connected to the main network, wastewater continued to be discharged at random, and the smell and mosquitoes persisted. On a villager's phone, the reporter saw that just days earlier, a villager had posted a video in the village group chat complaining that the channel in front of their home smelled of pig manure. Others said that because the plant was built, a school was brought in, but since the plant was never used and the school generates a large amount of sewage, the No. 2 drainage channel became even dirtier.
Guided by villagers, the reporter found a drainage pipe more than half a meter in diameter on the eastern side of the channel, discharging dark green sewage. Villagers said it was the school's outlet. The school has more than 2,000 teachers and students, and its domestic sewage is discharged there after simple treatment. In later interviews, local authorities said the school has its own sewage treatment facility that meets discharge standards. Villagers and shopkeepers said they had repeatedly asked relevant departments when the plant would be activated but received no answer, calling it a "vanity project" and "image project."
Why was the plant built but not used? A villager provided the reporter with a statement signed and sealed by the Luannan County Housing and Urban-Rural Development Bureau and the Hu'gezhuang Township People's Government, dated September 18, 2025. The statement said the project was completed in October 2022, but during testing, sand leakage and severe blockages were found in the pipeline and inspection wells from the Yinlong commercial building to the Changliang spinning mill, preventing the network from collecting and discharging sewage. As a result, the plant was not accepted or put into use. Judicial procedures have been initiated to determine the responsibilities of the survey, design, construction and supervision units, and the county people's court has accepted the case.
Jia Jingshu, director of the Luannan County Housing and Urban-Rural Development Bureau, confirmed that the project involved both plant construction and pipeline work, with 8 million yuan in special bond funds sought and a total investment of 8.87 million yuan, but it was never put into use due to pipeline problems. In addition to the plant and underground pipes, the road surface above the network has collapsed multiple times in recent years. Along the way, the reporter could clearly see uneven roads with signs of repair after collapses, broken or missing manhole covers, and some sewage wells filled with sand.
"After rain, water often accumulates, and we dare not ride electric bikes, let alone walk through," a shopkeeper said. While the plant sits unused, sewage is discharged directly into the channel. Li Zhinan, party secretary of Hu'gezhuang township, said there are more than 80 shops and over 1,500 villagers along the No. 2 drainage channel, as well as the township government, schools, a health center and enterprises. "Most of the water discharged into the channel has undergone simple treatment, but we admit it is still sewage," he said, adding that some shops may have connected sewage pipes to rainwater pipes, discharging untreated wastewater directly into the channel, and that littering during the Hu'gezhuang market fair along the route has worsened pollution.
Construction, design and survey units are blaming each other over the quality problems, and legal proceedings have been initiated. Local officials said the construction unit believes it built according to design standards and the project itself is fine, and that the design was the problem. The design unit blames preliminary survey work, saying the road was surveyed for ordinary rural traffic loads without considering heavy vehicles. Jia said the construction side denied problems, so a third-party company was brought in for appraisal. Experts found the main causes of sand leakage were vehicle rolling, detached concrete sealing rings and water level differences, and recommended legal action against the survey, design, construction and supervision units.
Asked whether the housing and construction bureau bore regulatory responsibility, Jia said it is the administrative department for the plant, while the county urban construction and development company was the contracting unit. The bureau should have exercised some oversight, but "during construction, the local area was Hu'gezhuang, and on-site management was handled by the township, and no problems were found." Some residents said the full project payment was disbursed before the plant was accepted, leaving no one responsible when problems arose. The bureau denied this. Jia said payments were made according to the contract and progress, with more than 7.3 million yuan paid so far, about 170,000 yuan left unpaid for pipeline work as a quality guarantee, and about 1.38 million yuan unpaid for equipment installation and infrastructure at the plant.
The bureau also disagreed with residents' description of the plant as a "vanity project" or "image project." Jia said the project was never an image project at any stage from planning to construction. He said the bureau had considered having the government advance funds to restore the pipeline and road surface and put the plant into operation while judicial procedures proceeded. In 2024, the bureau asked a company to survey and design the pipeline restoration, formulate a plan and complete a review, estimating 2.31 million yuan would be needed. But legal counsel argued that restoring it first would damage the site and make it impossible to determine the responsibility of the four units, so the plan was not implemented.
Local authorities have filed a lawsuit asking the court to determine responsibility and recover losses. The court accepted the case in 2025 and is conducting testing and appraisal of the project. Regarding worsening pollution in the No. 2 drainage channel due to the plant's inactivity, Li said daily cleanup will be strengthened, including mobilizing local enterprises and residents to participate. A villager told the reporter that in spring this year, the government organized excavators to spend half a month clearing large amounts of garbage and sludge, but the villager believed this only treated the symptoms, not the root cause.
Jia said pollution in the channel certainly affects residents' quality of life. "We consulted environmental protection departments, and before the plant is put into use, the only fundamental solution is interception, transporting sewage and sludge to a treatment plant, but the cost is too high. Only when the plant is activated can this section of polluted water be fundamentally treated," he said. A official from the Luannan county party committee said the county must bear responsibility for the pipeline connection and subsequent operation of the Hu'gezhuang township plant. The county people's court will speed up hearings in accordance with laws and regulations, the county water bureau has proposed a multi-million-yuan dredging project for the No. 2 drainage channel and is applying for funds, and meanwhile, interception measures including water dilution and chemical treatment are being used to clean sludge.
As of press time, local authorities had begun clearing garbage from the No. 2 drainage channel. The activation of the Hu'gezhuang township sewage treatment plant remains under continued attention.