Yancoal Aus released a Hong Kong-compliant Competent Person’s Report (CPR) on the Kestrel underground operation in Queensland’s Bowen Basin, ahead of completing the 80% acquisition of Kestrel Coal Resources.
Key resource and reserve metrics • Coal Resources (inclusive of Reserves): 397 million tonnes (Mt) at 6 % in-situ moisture, comprising 97 Mt Measured and 280 Mt Indicated. • Coal Reserves: 209 Mt run-of-mine (ROM), split 67 Mt Proved and 142 Mt Probable; marketable Reserves of 156 Mt. • Estimates adhere to the 2012 JORC Code and capture data to 30 June 2026.
Life-of-mine profile • Operating horizon: 2026-2052 (26 years). • Average annual output: 8.00 Mt ROM and 6.00 Mt saleable coal at a 75 % yield. • Product mix: hard coking coal dominates to 2035, transitioning to semi-soft coking coal in later years; thermal coal averages 11 % of total product.
Operating economics • Forecast free-on-rail cash cost: A$78.76/t product. • Forecast free-on-board cash cost: A$112.00/t product, excluding royalties. • Planned capital programme: A$3.72 billion, including A$2.37 billion sustaining and A$0.64 billion growth tied to the Kestrel West expansion.
Mining and processing assumptions • Single longwall supported by three continuous-miner units; panel widths up to 414 m and lengths to 5.8 km. • Existing 1,500 t/h CHPP upgraded in 2023; modelling assumes 6.5 %-ash hard coking coal until 2041, then 8.5–9.0 %-ash semi-soft coking coal. • Rail haulage via the Blackwater system to Gladstone’s RG Tanna Coal Terminal, where Yancoal holds dedicated stockpile capacity.
Regulatory status • All current production is covered by five Mining Leases; future output depends on converting MDL 182 to a Mining Lease by 2030 and securing associated environmental approvals for Kestrel West.
Risks and opportunities • Risks: approval timeline for Kestrel West, tailings storage expansion after 2031, management of frictional ignition events. • Opportunities: CHPP yield optimisation, longwall move-time reductions, potential bord-and-pillar recovery between existing panels, and methane abatement projects that could lower costs and emissions.
ESG highlights • Estimated rehabilitation liability: A$99.20 million (ERC). • Proposed 30 MW coal-mine-waste-gas power station and a ventilation-air-methane project are designed to cut Scope 1 emissions and generate Australian Carbon Credit Units.
The CPR concludes that, subject to timely approval of Kestrel West, no material factors impede extraction of the declared Reserves or the planned acquisition.