Tianjin Completes 132.49 Kilometers of Aging Water Supply Pipe Network Renovation, Marking Significant Year-on-Year Progress Increase

Deep News15:00

Tianjin has completed 132.49 kilometers of aging water supply pipe network renovation, with progress rising substantially compared to the same period in previous years.

According to information from a press conference held by Tianjin's State-owned Assets Supervision and Administration Commission on the 19th, 2026 marks the opening year of the "15th Five-Year Plan," and Tianjin Water Group is accelerating the renovation of aging water supply pipe networks. The annual plan targets 150 kilometers of renovation, and as of the press conference, a cumulative total of 132.49 kilometers had been completed, representing a significant year-on-year increase in both the completed volume and completion ratio compared to previous years.

A representative from Tianjin Water Group explained that as the core force behind Tianjin's water supply security, the group adheres to a problem-oriented approach, treating residents' water usage demands as both the starting point and the ultimate goal. The group comprehensively assesses factors such as pipeline service life, public repair requests, and on-site inspections, giving priority to projects with concentrated public complaints and urgent renovation needs.

Among this year's renovation tasks, the DN500 pipe network renovation along Youyi Road is the top priority. This road section is a core arterial road in Tianjin's urban area, connecting 5 aging residential communities with 3,500 households and 11 key public service units along its route. The project commenced on March 3 and was fully completed and connected to the water supply on August 16, half a month ahead of the planned schedule. After renovation, the pipe network operates stably with all indicators meeting standards.

During implementation, Tianjin Water Group adhered to the principles of "less excavation, less disturbance to residents, ensuring traffic flow, and ensuring water supply." For the first time in Tianjin's water supply pipe network renovation, the group introduced a laminated in-situ curing trenchless repair technique and adopted a nighttime construction model to minimize the impact on traffic and residents' daily lives, making it a benchmark project for civilized construction in Tianjin's municipal engineering.

In addition, Tianjin Water Group has established a "one-number response, multi-party coordination" service system, with the "96655" water supply hotline operating AI plus human-staffed round-the-clock service, 7 days a week. This year, the hotline received a total of 914,000 incoming calls, with an AI response rate of 24.96%, a call connection rate of 97.57%, a work order processing and response rate of 100%, and a work order follow-up satisfaction rate of 99.34%.

Disclaimer: Investing carries risk. This is not financial advice. The above content should not be regarded as an offer, recommendation, or solicitation on acquiring or disposing of any financial products, any associated discussions, comments, or posts by author or other users should not be considered as such either. It is solely for general information purpose only, which does not consider your own investment objectives, financial situations or needs. TTM assumes no responsibility or warranty for the accuracy and completeness of the information, investors should do their own research and may seek professional advice before investing.