Baowu's Simandou North Mine Completes Full-Chain Construction, 60 Million Tonne Annual Capacity Fully in Place

Deep News11-19 11:50

China Baowu announced on November 10 that on November 6 local time, the final critical process of the Baoying Simandou Mine Phase 2 — the heavy-load trial run of the CS zone downhill conveyor belt system — succeeded on its first attempt, marking the completion and commissioning of Phase 2. With this, the Simandou North Mine project has achieved full completion of its entire industrial chain spanning mine, railway, and port, and the project has fully transitioned from the construction phase to the operational phase. A world-class iron ore project with total investment exceeding US$20 billion and planned annual capacity of 60 million tonnes has moved from blueprints to steady output.

Phase 1 and Phase 2 Completion: The Final Link in the Full Chain Is Now Connected

This commissioning occurred on the one-year anniversary of Phase 1 production at the Baoying Simandou Mine, with China Baowu General Manager Hou Angui witnessing the event on site. The construction of Phase 2 was no easy feat — complex geological conditions, short rainy-season construction windows, and long cross-border supply chains posed significant challenges. Two major control works were overcome: the safe breakthrough of the CV3 conveyor tunnel and the full-line heavy-load trial run of the CS zone downhill conveyor system, culminating in full commissioning on November 6.

On the Phase 1 side, production has continued to ramp up since first-phase commissioning in November 2025. Baowu has taken the lead in strengthening the "Simandou integrated production-transportation-sales" operational management system, continuously optimizing the entire production chain from pit mining, crushing and processing, stockyard storage to railway loading, effectively boosting daily output. Cumulative production and shipment of finished ore has exceeded 10 million tonnes. With both phases in place, this means the planned capacity framework of 60 million tonnes per year for the northern block has been fully realized, and the project's focus has officially shifted from "construction" to "operations."

Project Overview

Six-Year Marathon: From Initial Engagement to Controlling Stake and Operations

The Simandou project's mine is divided into northern and southern blocks. The northern block comprises mining areas No. 1 and No. 2, along with supporting railway and port infrastructure. Baowu's participation has followed a clear progressive path: in 2020, Baowu began engagement with the Winning Consortium on the northern block, actively facilitating rapid collaborative development of Simandou with the Winning Consortium, Rio Tinto, Chinalco, and the Guinean government. In June 2024, Baowu formally acquired a 49% equity stake in the northern mine. In November 2025, Baowu, in coordination with all shareholders and construction units, achieved Simandou project commissioning two months ahead of schedule. According to public reports, the first shipment of ore set sail in December of that year and arrived in China in January 2026. In January 2026, Baowu increased its stake to 51%, becoming the controlling shareholder of the northern mine. In November 2026, Phase 2 was completed and commissioned, with the entire industrial chain of mine, railway, and port fully built.

From an equity perspective, according to public reports, the railway infrastructure company connecting the mining area to the port is held 42.5% each by the northern and southern block joint venture parties, with the Guinean government holding 15% — this is a joint venture structure jointly advanced by the Guinean government, Chinese enterprises, and international partners, rather than a solo act by any single party.

Why Simandou: Grade Is Leverage

Simandou's value lies fundamentally in its grade. The northern block has an iron grade of 65.28%, classifying it as a world-class high-quality open-pit hematite deposit. The higher the grade, the greater the iron content per unit of ore, and the relatively lower the pressure of impurity processing — a tangible benefit for ironmaking costs and energy consumption. Against the backdrop of the steel industry's green and low-carbon transition, the premium logic for high-grade feedstock will only grow stronger.

The southern block is being developed by Rio Tinto through SimFer for mining areas No. 3 and No. 4, with partners including Chinalco-related investment entities and the Guinean government. According to Rio Tinto's official website, mining areas No. 3 and No. 4 have ore reserves of approximately 1.5 billion tonnes, including 200 million tonnes of proven reserves at 66.4% iron grade and 1.3 billion tonnes of probable reserves at 65.0% iron grade (note: these are reserve figures, which differ from the resource figures disclosed by Baowu for the northern block and should not be directly compared). With both the northern and southern wings in full swing, the Simandou project's long-term export capacity is approximately 120 million tonnes per year.

Putting this in the context of the Chinese market: data from the National Bureau of Statistics shows that China imported 1.259 billion tonnes of iron ore and concentrate in 2025. Once fully ramped up, 120 million tonnes would represent roughly one-tenth of imports — not enough to overturn the landscape, but enough to add a heavyweight player to the supply side of global high-grade iron ore.

The Real Barrier: A 620-Kilometer Railway and a Deep-Water Port

Simandou entered the视野 of international mining companies as early as the last century, yet lay dormant for nearly three decades — the constraint was never the ore itself, but infrastructure. The mining area is located in the inland southeast of Guinea, more than 600 kilometers from the coast. Without railways and ports, no matter how good the ore is, it cannot leave the mountains.

Therefore, the true significance of this project lies in the words "full chain": the mine, railway, and port must be built simultaneously and matched to each other. The Trans-Guinean Railway connecting the mining area to the Morebaya Port has a total length of approximately 620 kilometers, with supporting coastal port, barge terminal, and offshore transshipment facilities. In September of this year, Rio Tinto and project partners completed key financing approvals and capital injections, investing more than US$620 million to upgrade the railway corridor, supporting the project's total export capacity of approximately 120 million tonnes per year. This is also why Baowu repeatedly emphasizes "integrated production-transportation-sales" — for a logistics artery of over 600 kilometers directly connecting mine to port, whether the system can operate continuously and stably is more decisive than single-point capacity.

In May of this year, four new electric locomotives manufactured in China were put into operation on the Trans-Guinean Railway, fully opening the iron ore transportation corridor from the mining area to the port.

ESG Ledger: Hard Targets Beyond Production Volume

The Simandou mine, railway, and port all strictly align with IFC Performance Standards and the Equator Principles, advancing ESG governance under the philosophy of "co-building, co-progressing, and sharing":

— Environmental side: Biodiversity management is carried out at all levels, with large-scale ecological restoration completed along the mine and railway; an Environmental Product Declaration (EPD) for iron ore has been published, electric mining trucks have been deployed at scale, and clean energy substitution is being actively promoted.

— Social side: During the peak construction period, more than 60,000 jobs were created for local communities, with a localization employment rate of 73%. Community roads, schools, hospitals, and other infrastructure are being comprehensively advanced.

For Guinea, this is an engine for economic and social development; for the project partners, this ESG system is a moat for long-term operating licenses. During his inspection, Hou Angui also explicitly required that subsequent operations must strictly adhere to safety and environmental bottom lines, coordinate green energy supporting facilities, and unswervingly pursue a low-carbon operational path.

What to Watch Next

1. Ramp-up pace. Full commissioning does not equal immediately reaching design capacity — the 60 million tonne annual capacity is still ramping up. For reference: Rio Tinto's third-quarter operations report disclosed that the Simandou project has reached a production rate of approximately 10 million tonnes on an annualized basis; the southern SimFer mine is also planned at 60 million tonnes per year and is expected to reach full production in the second half of 2028. How the northern ramp-up curve unfolds will directly determine when the global shipment inflection point appears.

2. Operational efficiency. Hou Angui put forward four requirements for follow-up work: strictly adhere to safety and environmental bottom lines, solidly grasp integrated production-transportation-sales coordination, benchmark against first-class standards to build an international model mine, and solidify the foundation of localized talent. Full-chain cost accounting, production efficiency, logistics organization — mine completion is only the passing line; operational capability is the long race.

3. Supply landscape. China's iron ore imports have long relied on two major sources: Australia and Brazil. After Simandou ramps up, buyers will have an additional high-grade option — in the short term, it cannot replace anyone, but full competition among suppliers is itself a source of buyer bargaining power. For steel raw material security, one more reliable channel means one more degree of initiative.

From a world-class ore deposit dormant for thirty years to the full connectivity of mine, railway, and port, Simandou has completed a thrilling leap from planning to supply in six years. The next chapter belongs to capacity ramp-up and operational delivery.

Disclaimer: Investing carries risk. This is not financial advice. The above content should not be regarded as an offer, recommendation, or solicitation on acquiring or disposing of any financial products, any associated discussions, comments, or posts by author or other users should not be considered as such either. It is solely for general information purpose only, which does not consider your own investment objectives, financial situations or needs. TTM assumes no responsibility or warranty for the accuracy and completeness of the information, investors should do their own research and may seek professional advice before investing.