On November 25, the Jiangsu Provincial Development and Reform Commission issued a notice regarding the launch of mechanism electricity price bidding for 2027 incremental new energy projects.
The bidding scope covers new energy power generation projects that achieve full-capacity grid connection between June 1, 2025 (inclusive) and December 31, 2027 (inclusive) and have not previously been included in the mechanism electricity price execution scope.
The bidding is divided into two categories: offshore wind power projects (including offshore wind-solar co-located projects, hereinafter the same) and other wind power and photovoltaic projects (including other offshore photovoltaic projects, hereinafter the same).
For the offshore wind power projects category, the bidding ceiling is 0.391 yuan/kWh and the bidding floor is 0.3 yuan/kWh. For the other wind power and photovoltaic projects category, the bidding ceiling is 0.391 yuan/kWh and the bidding floor is 0.2 yuan/kWh.
The total mechanism electricity volume for this bidding is 13 billion kWh, of which 500 million kWh is allocated to the offshore wind power projects category and 12.5 billion kWh to the other wind power and photovoltaic projects category.
The declared electricity volume scale for bidding shall be set at no less than 125% of the total mechanism electricity volume. If the declared electricity volume of all bidding projects falls below 125% of the total mechanism electricity volume, the total mechanism electricity volume shall be reduced accordingly.
If the number of valid declared projects in a relevant category is fewer than 5 (exclusive), no clearing shall be conducted, and the mechanism electricity volume scale for that category shall be reallocated for use by other categories to carry out incremental project bidding.
The upper limit for the declared bidding electricity volume ratio of a single project shall not exceed 90% of its estimated annual on-grid electricity volume. The estimated annual on-grid electricity volume shall not exceed the on-grid electricity volume converted from the average power generation utilization hours of similar projects in the province over the past three years.