On November 11, Talen rose 5.19% in Pre-Market Trading, trading at $379.94 per share, with turnover of $1.1198 million.
The move followed the company’s announcement of a seven-year capacity agreement to supply 750 megawatts in the PJM market to an investment-grade counterparty, a contract expected to generate about $100 million in annual revenue.
The agreement covers delivery years 2029/2030 through 2035/2036, with supply from the Guernsey Power Station. Talen said the deal, together with capacity cleared through auctions, provides about 10 years of capacity revenue visibility totaling roughly $1 billion for the 750 MW. The company also said that, combined with its long-term contract with AWS, the contracted share of gross margin rises to 40% through 2036, improving cash flow durability and visibility.