25-Day Intensive Effort: 10KV High-Voltage Power Transmission Successfully Completed at Ulanqab VNET Project

Deep News05-13 16:10

Recently, a critical construction milestone was achieved at the Ulanqab VNET Group Zero-Carbon Intelligent Computing Center Base Phase I Project, specifically for the A1 (North Side) Data Center Building managed by China Construction Second Engineering Bureau First Company Installation Branch. The 10KV high-voltage power transmission was successfully completed in a single attempt, marking the project's official entry into the equipment commissioning and operational preparation phase, laying a solid foundation for subsequent overall handover.

The 10KV power transmission task was characterized by a tight schedule, high standards, and complex overlapping operations. Within a demanding 25-day攻坚周期, the project team completed the core task of laying 560,000 meters of electrical wires and cables. During construction, the team faced multiple challenges, including dense arrangements of electromechanical pipelines, limited worksite space, and the interwoven construction of multiple specialties and trades. All personnel involved proactively gave up轮休假期, working in昼夜轮班奋战一线.

The site strictly implemented the organizational principle of "zoning by平面, time-sharing by space, and staggered peak-hour穿插施工," meticulously coordinating工序衔接, strictly controlling construction safety and工艺 standards, and efficiently resolving various construction bottlenecks, ultimately achieving the goal of successful one-time power transmission.

Beyond cable laying, the project also completed the high-standard installation of various core power equipment, line调试, and supporting construction such as fireproof sealing. A total of 36 transformers, 36 sets of power modules, 68 medium-voltage cabinets, 154 column头柜, 110 battery switchgear cabinets, and 405 small三箱 were delivered to the site and installed. All equipment was installed and commissioned precisely according to design specifications and timelines, with all units operating in good condition, establishing a solid hardware foundation for the successful 10KV power transmission and stable future power supply.

"This is a critical milestone node for the project's construction. The successful achievement is inseparable from the overall deployment and on-site指挥 of the branch leadership and, more importantly, is owed to every team member坚守一线 and冲锋在前," stated Project Manager Niu Yanbo.

To ensure the high-voltage power transmission node was met on schedule, the project department deployed 530 personnel during the peak construction period, implementing high-intensity, highly coordinated穿插作业. Simultaneously, the project department placed great emphasis on safety production and labor management, recently organizing a monthly safety education conference that covered over 300 frontline workers. The conference systematically disseminated operating procedures, job hazard notifications, and emergency response processes, with现场 demonstrations on the proper use of personal protective equipment such as safety helmets and harnesses, comprehensively enhancing全员 safety awareness and self-protection and mutual protection capabilities.

According to reports, the Ulanqab Zero-Carbon Intelligent Computing Center Base Phase I Project is located in the Ulanqab High-Tech Zone. The construction scope encompasses specialized engineering works including弱电, HVAC, plumbing and drainage, electrical, fine装修, and rooftop steel structures. Upon completion, the project will promote the construction of the Ulanqab Zero-Carbon Intelligent Computing Center, elevate regional digital infrastructure水平, assist the development of the green computing power industry, and inject new momentum into the high-quality development of the数字 economy in Inner Mongolia.

In the next phase, the project team will continue to maintain its攻坚态势, steadily advancing subsequent construction tasks for机电安装, fine装修, and rooftop steel structures. The team will strictly implement the principles of "sample first, quality excellence, and safety control" to ensure the project is completed and delivered as soon as possible,助力 Ulanqab in building a green, efficient, and intelligent zero-carbon computing power hub.

Disclaimer: Investing carries risk. This is not financial advice. The above content should not be regarded as an offer, recommendation, or solicitation on acquiring or disposing of any financial products, any associated discussions, comments, or posts by author or other users should not be considered as such either. It is solely for general information purpose only, which does not consider your own investment objectives, financial situations or needs. TTM assumes no responsibility or warranty for the accuracy and completeness of the information, investors should do their own research and may seek professional advice before investing.