Seatrium Limited announced on Nov, 19 2026 that it has maintained a steady revenue run rate and achieved further gross-margin expansion in the third quarter ended Sep, 30 2026, supported by a favourable project mix, continued cost discipline and savings from non-core divestments.
The group has secured 1.7 billion Singapore dollars in new orders year to date, lifting its net order book to 12.2 billion Singapore dollars across 35 projects with deliveries scheduled through 2033. Recent awards include three floating storage and regasification unit conversions for Karpowership and Excelerate Energy, FPSO integration work for SBM Offshore and MODEC, and five Whale Class powership conversions for Karpowership.
Operationally, Seatrium delivered the offshore substations for Ørsted’s Revolution Wind project, the Sparta floating production unit for Shell, and achieved the dual sailaways of FPSOs P-80 and P-82 for Petrobras. Recurring annualised cost savings of more than 50 million Singapore dollars from completed divestments remain on schedule, with further initiatives ongoing.
The company reiterated its focus on projects that offer risk-adjusted mid-teens margins and progressive milestone payments, alongside continued cost optimisation. Management expects underlying full-year 2026 net profit, excluding one-off items, to be materially higher than that of 2025.
Comments