An official notice has been released regarding a sewage treatment plant built at a cost of more than 8 million yuan that was never put into operation.
According to a joint investigation team's notice dated November 16, released via the "Luannan Promotion" WeChat public account, the issue of the sewage treatment plant in Hugezhuang Town, Luannan County, being completed but never used has drawn significant attention from the Tangshan Municipal Party Committee, the Tangshan Municipal Government, the Luannan County Party Committee and the Luannan County Government. A joint municipal and county investigation team has been established to conduct a comprehensive review, and those responsible will be dealt with strictly in accordance with laws and regulations based on the investigation results.
Previously, according to a report, a netizen left a message claiming that the Luannan County government in Hebei Province invested more than 8 million yuan to build the Hugezhuang Town sewage treatment plant, which had never been activated since its completion. Reporters visited Luannan County for investigation and interviews and found that part of the fence on the west side of the Hugezhuang Town sewage treatment plant had collapsed. Weeds had spread across the plant grounds, with cabbage, corn and other crops planted in some areas and agricultural plastic film covering others. No signs of any machinery in operation could be seen.
A public notice board hanging outside the equipment room stated that Hugezhuang Town, as a provincial-level distinctive town, was required by higher-level housing and construction authorities to complete the construction of town-level sewage treatment facilities. In September 2018, with county government approval, Luannan County Urban Construction Development Co., Ltd. (a subsidiary of the county housing and construction bureau) undertook the project, with an estimated total investment of 8.18 million yuan.
Jia Jingshu, director of the Luannan County Housing and Construction Bureau, confirmed that the Hugezhuang Town sewage treatment plant involved two parts — plant construction and pipeline network construction — with 8 million yuan in special bond funding secured and a total investment of 8.87 million yuan. However, due to pipeline issues, the plant had never been put into use.