SK hynix (SKHY.US) announced on Monday that it will partner with the South Korean government to open a semiconductor testing facility next year, aimed at boosting the global competitiveness of South Korea's small and mid-sized chip equipment manufacturers.
The facility, costing 874.6 billion won (approximately $654 million), is being built within the Yongin semiconductor industry cluster currently under construction south of Seoul.
The company stated in a press release that the facility, named Trinity Fab, will begin operations in May and will be equipped with tools accessible to small and mid-sized suppliers for completing final performance and yield validation before products enter commercial chip production lines.
The facility will house approximately 50 pieces of equipment for lithography, etching, deposition, cleaning, and metrology, allowing suppliers to test products on 12-inch wafers under conditions close to commercial chip production.
Currently, SK hynix and its domestic rival Samsung Electronics are enjoying unprecedented price increases driven by the chip shortage — industries from automotive to smartphones are being squeezed by tight supply.
The company said it is working with the South Korean government to eliminate a key bottleneck in the country's supply chain: previously, access to expensive manufacturing infrastructure was required to complete validation.
However, there was previously no public channel for small and mid-sized materials and equipment companies to obtain production-grade testing capabilities.
According to the company, the facility is jointly funded by SK hynix, the South Korean central government, and local governments.
Smaller materials and equipment manufacturers have long faced challenges such as high costs and long timelines for accessing production-grade testing facilities, making it difficult to prove that their technologies can meet the stringent performance and yield requirements of advanced chip manufacturing.
SK hynix stated that unlike conventional research laboratories and pilot lines, Trinity Fab will be the world's first open testing facility specifically designed to validate mass production readiness.
However, the center will be operated by an independent non-profit foundation to protect the intellectual property of participating parties.
In August of this year, SK hynix said it would spend $38 billion to expand its domestic chip manufacturing facilities, including building a new DRAM plant in Yongin and a new NAND plant in Cheongju.
The company said at the time that the move covers both low-latency dynamic storage and high-speed high-capacity solid-state storage, responding to growing storage demand in the AI era.