FACTBOX-How Germany is building up LNG import terminals

Reuters12-02
FACTBOX-How Germany is building up LNG import terminals

Updates with Wilhelmshaven 2 and Brunsbuettel re-installing their FSRUs ready for winter, status of DET's Wilhelmshaven 1 and 2 capacity auctions, Mukran data from Deutsche ReGas

FRANKFURT, Dec 2 (Reuters) - Germany has been putting import terminals for liquefied natural gas into operation as part of its efforts to replace piped Russian gas following Moscow's invasion of Ukraine in 2022.

The Brunsbuettel terminal received its floating storage regasification unit, the Hoegh Gannet, back on November 24 after upgrades, and Wilhelmshaven 2 has restarted its FSRU Excelsior ready for the coming winter months, state-appointed terminal company Deutsche Energy Terminal said.

DET, which is in charge of three terminal locations, has said it will rerun auctions for LNG landing capacity at Wilhelmshaven 1 and 2 in December, having so far failed to place a variety of slots. It has fed 59 terawatt hours into German grids so far this year.

Here are the details of developments at the sites:

MUKRAN

The terminal on Ruegen island in the Baltic Sea operated by private firm Deutsche ReGas supplies onshore grids with LNG from pipeline firm Gascade's OAL link, in cooperation with Norway's Hoegh Evi's FSRU Neptune.

It wants to restart a second FSRU eventually and restore full capacity of 13.5 billion cubic metres by 2027.

ReGas has launched a bidding round to expand Mukran's capacity by offering an additional 5 billion cubic metres per year from 2027 to 2043.

In September, it signed long-term agreements with chemicals producer BASF BASFn.DE and Norwegian incumbent Equinor EQNR.OL for non-specified regas capacity.

The company said it regasified 8.35 TWh of LNG in October and November, holding first place ahead of each of the other three working LNG terminals.

LUBMIN

ReGas and Hoegh plan to develop the Baltic Sea port, a forerunner of Mukran, into a green ammonia and hydrogen production and import terminal, which Gascade will link up with customers.

WILHELMSHAVEN

Utility Uniper UN01.DE launched Germany's first FSRU operation, Wilhelmshaven 1, on the North Sea in 2022.

Uniper plans to add a land-based ammonia import reception terminal and cracker in the second half of this decade to make green hydrogen, and build a 200 MW electrolyser to be fed with local wind power.

DET officially started commercial operations at Wilhelmshaven 2 on August 29 via the Excelerate Energy-operated FSRU Excelsior. Maintenance also took place in October.

In auctions on November 25-26, DET failed to place some available regasification slots in 2025, 2026 and 2027 with gas market players, and will repeat them on December 9 and 10.

STADE

DET has agreed with the Hanseatic Energy Hub to take on the job of erecting an FSRU superstructure at the Elbe River onshore terminal.

DET said it would start on the inspection, planning and execution of the job, but added that the terminal would not be ready to go into operation before the second quarter of 2026.

The FSRU Energos Force would return to the site, where Uniper and sector peer EnBW EBKG.DE will be the main customers.

Prior to the latest developments, DET and HEH had temporarily cancelled contracts with each other over unresolved disputes related to construction schedules and payments.

HEH plans to start a shore-based terminal for LNG, bio-LNG and synthetic natural gas at Stade in 2027.

BRUNSBUETTEL

The Hoegh Gannet was removed temporarily in September for upgrades. These were completed and the ship returned on November 24 to the North Sea port.

It went into operation in 2023 in Brunsbuettel, initially chartered by the trading arm of utility RWE RWEG.DE, before being handed over to DET.

It is the forerunner of a land-based LNG facility, cleared to receive 40 million euros ($46.4 million) of state support.

This could start operations at the end of 2026, when a newly inaugurated, adjacent ammonia terminal could also start up.

($1 = 0.8618 euros)

(Reporting by Vera Eckert; Editing by Jan Harvey)

((vera.eckert@thomsonreuters.com; +49 30 2201 33654))

Disclaimer: Investing carries risk. This is not financial advice. The above content should not be regarded as an offer, recommendation, or solicitation on acquiring or disposing of any financial products, any associated discussions, comments, or posts by author or other users should not be considered as such either. It is solely for general information purpose only, which does not consider your own investment objectives, financial situations or needs. TTM assumes no responsibility or warranty for the accuracy and completeness of the information, investors should do their own research and may seek professional advice before investing.