Macmahon Holdings' (ASX:MAH) Decmil unit received a AU$51 million contract from Tilt Renewables for works at the Waddi Windfarm in Western Australia, according to a Wednesday filing with the Australian bourse.
The deal includes the design and construction of the balance of plant for the wind farm, the filing said.
The company expects to start the works in early 2026 and complete them by early 2027, the filing added.
It retained its fiscal 2026 revenue guidance of AU$2.6 billion to AU$2.8 billion and underlying EBIT(A) of AU$180 million to AU$195 million.
Disclaimer: Investing carries risk. This is not financial advice. The above content should not be regarded as an offer, recommendation, or solicitation on acquiring or disposing of any financial products, any associated discussions, comments, or posts by author or other users should not be considered as such either. It is solely for general information purpose only, which does not consider your own investment objectives, financial situations or needs. TTM assumes no responsibility or warranty for the accuracy and completeness of the information, investors should do their own research and may seek professional advice before investing.
Comments