Supreme Court Rejects Enbridge's Bid to Move Pipeline Case to Federal Court

MT Newswires Live04-22

The US Supreme Court on Wednesday rejected Enbridge's (ENB) motion to move a lawsuit seeking to halt the company's operation of the Line 5 pipeline from Michigan state court to federal court.

The attorney general for the state of Michigan filed the lawsuit in June 2019 in state court seeking to block Enbridge from operating the 645-mile-long pipeline that runs from northwestern Wisconsin through Michigan and into Canada.

"The Court of Appeals therefore correctly held that Enbridge's notice of removal was untimely and that this action must be remanded to the Michigan state court," said Justice Sonia Sotomayor, who delivered the opinion for the court. "The judgment of the Court of Appeals is affirmed."

Enbridge didn't immediately reply to a request for comment from MT Newswires.

Price: 51.92, Change: +0.06, Percent Change: +0.13

Disclaimer: Investing carries risk. This is not financial advice. The above content should not be regarded as an offer, recommendation, or solicitation on acquiring or disposing of any financial products, any associated discussions, comments, or posts by author or other users should not be considered as such either. It is solely for general information purpose only, which does not consider your own investment objectives, financial situations or needs. TTM assumes no responsibility or warranty for the accuracy and completeness of the information, investors should do their own research and may seek professional advice before investing.