Ahmad Zaki Resources Unit Faces MYR2 Million Winding-Up Petitions

MT Newswires Live07-14 12:22

Ahmad Zaki Resources (KLSE:AZRB) unit Ahmad Zaki has been served with two winding-up petitions by Tenaga Nirwana, and Muhibbah Engineering (M), involving combined claims of about 1.8 million ringgit.

The Tenaga Nirwana petition seeks 1.5 million ringgit for works on the Kuantan Flyover, East Klang Valley Expressway (EKVE) and MRT V6 projects, while the Muhibbah Engineering petition claims 319,901.9 ringgit for works on the MRT2 Sungai Buloh-Serdang-Putrajaya (SSP) V202 project.

Ahmad Zaki is in discussions with both petitioners to reach an amicable settlement and does not expect the petitions to have a significant financial or operational impact.

Disclaimer: Investing carries risk. This is not financial advice. The above content should not be regarded as an offer, recommendation, or solicitation on acquiring or disposing of any financial products, any associated discussions, comments, or posts by author or other users should not be considered as such either. It is solely for general information purpose only, which does not consider your own investment objectives, financial situations or needs. TTM assumes no responsibility or warranty for the accuracy and completeness of the information, investors should do their own research and may seek professional advice before investing.

Comments

We need your insight to fill this gap
Leave a comment