Eni (E) said Wednesday it generated first industrial electricity from the 120-megawatt gas power plant at the 247-MW Mangystau Hybrid Power Plant in Kazakhstan.
The company said the project, developed with KazMunayGas and Eni subsidiary Plenitude, is Kazakhstan's first large-scale hybrid power plant, combining solar, gas and planned wind generation.
Eni said the project's 50-MW solar plant began operating in September 2025, while the gas plant is expected to be fully commissioned in Q3.
A 77-MW wind farm is scheduled to begin operations in 2027, completing the hybrid facility, it added.
Disclaimer: Investing carries risk. This is not financial advice. The above content should not be regarded as an offer, recommendation, or solicitation on acquiring or disposing of any financial products, any associated discussions, comments, or posts by author or other users should not be considered as such either. It is solely for general information purpose only, which does not consider your own investment objectives, financial situations or needs. TTM assumes no responsibility or warranty for the accuracy and completeness of the information, investors should do their own research and may seek professional advice before investing.
Comments