Press Release: I-80 Gold Reports Second Quarter 2026 Results; on Track to Achieve Full-Year Guidance as Granite Creek Ramps up and Development Plan Advances

Dow Jones06:17

TORONTO, Aug. 10, 2026 /CNW/ -- i-80 GOLD CORP. (NYSE:IAUX) (TSX:IAU) ("i-80 Gold" or the "Company") reports its financial and operating results, as well as development highlights, for the three and six months ended June 30, 2026.

"We delivered another solid quarter, with increased production from Granite Creek as the project continued to ramp up on plan, the advancement of Archimedes on schedule toward becoming our second underground mine, and the start of demolition at the Lone Tree Plant," stated Richard Young, President & CEO. "Additionally, Archimedes drilling results released during the quarter demonstrated the vast exploration potential and the ability to extend its mine life. Our success year-to-date demonstrates the Company's ability to advance multiple projects concurrently. We remain on track to commence gold mining at Archimedes and major construction at Lone Tree in the fourth quarter of this year, marking two important milestones by year-end as we execute our development plan to build a Nevada-focused mid-tier gold producer."

SECOND QUARTER HIGHLIGHTS

Three months ended June 30, 2026 compared to three months ended June 30, 2025.

Unless otherwise stated, all amounts referred to herein are in U.S. dollars.

Development

   -- Granite Creek underground development continued ahead of plan increasing 
      access to high-grade headings supporting the ongoing ramp up. The project 
      remains on track to achieve its full-year production guidance, with a 
      published feasibility study anticipated in the third quarter of 2026. 
 
   -- Archimedes underground advanced on schedule and largely on budget with 
      the main decline development on track, advancement of the exploration 
      drift, which has since been completed, and commencement of the 
      ventilation raise in preparation for first gold mined by year-end. 
 
   -- Lone Tree Plant refurbishment advanced on schedule and on budget as early 
      works and pre-construction readiness activities continued during the 
      quarter, and the commencement of demolition mid-June ahead of major 
      construction. Procurement activities remain on schedule, with 
      approximately 50% of procurement packages, by value, awarded as of 
      mid-July. Project capital remains on budget with minimal contingency 
      drawdown and approximately 40% of capital committed as of mid-July. 
 
   -- Completed approximately 19,000 meters of drilling across three projects, 
       including infill drilling at Archimedes underground and Mineral Point 
      open pit in support of planned 2027 technical studies for both projects, 
      as well as resource definition drilling at Granite Creek underground 
      beyond the area covered by the upcoming feasibility study. 
 
   -- Permitting largely on track across the development plan as permitting 
      actions continued to advance across the portfolio. 

Financial and Operating

   -- Revenues were $24.3 million, representing 5,335 ounces in gold sold(2) at 
      an average realized gold price(1) of $4,522 per ounce, compared to $27.8 
      million represented by 8,400 ounces at an average realized gold price(1) 
      of $3,301 per ounce in the prior year period. The decrease in revenues 
      was primarily driven by lower gold sold at Granite Creek as a result of 
      delays at the third-party processing facility, partially offset by a 
      higher average realized gold price(1). Revenues in the prior year quarter 
      were higher due to the finalization of the third-party toll processing 
      agreement in March 2025 and the processing of a higher volume of 
      stockpile material. 
 
   -- Gold production increased to 11,098 ounces from 4,178 ounces in the prior 
      year period. The Company remains on track to achieve its full year 
      production guidance range. 
 
   -- Gross profit increased to $8.6 million from $0.8 million in the prior 
      year period due to a higher realized gold price. 
 
   -- Net loss increased to $52.5 million compared to $30.2 million in the 
      prior year period, due primarily to higher pre-development, evaluation 
      and exploration costs incurred as the Company advances multiple projects 
      within its development plan. The higher costs were related to drilling 
      programs at the Ruby Hill property. Upon declaration of mineral reserves, 
      certain pre-development, evaluation and exploration expenditures that are 
      currently expensed will be capitalized. 
 
   -- Net loss per share increased to $0.06 compared to a $0.05 loss in the 
      prior year period, primarily due to a higher net loss, partially offset 
      by an increase in the weighted average number of common shares 
      outstanding following the equity financing in May 2025. 
 
   -- Adjusted net loss(1) increased to $41.2 million compared to $26.5 million 
      in the prior year period due to increased spending on pre-development, 
      evaluation and exploration expenses, partially offset by higher gross 
      profit. 
 
   -- Cash used in operating activities increased to $49.6 million compared to 
      $11.3 million in the prior year period as a result of comparative working 
      capital changes of $20.9 million primarily as a result of increased 
      inventory due to third-party processing availability and higher 
      pre-development, evaluation and exploration expenses which was partially 
      offset by higher gross profit. 
 
   -- Cash and cash equivalents were $464.6 million as of June 30, 2026, a 
      decrease of $49.0 million compared to March 31, 2026, primarily due to 
      cash used in operations of $49.6 million, capital expenditures of $21.5 
      million primarily driven by the start of the Lone Tree Plant 
      refurbishment project partially offset by a release of restricted cash of 
      $16.9 million and proceeds from warrant exercises. 

Sustainability

   -- Advanced community engagement across Northern Nevada by progressing 
      community development, workforce development, and grant funding 
      initiatives, including a joint $300,000 donation with Franco-Nevada 
      Corporation to support development of the first licensed childcare 
      facility in Eureka County, neighboring the Company's Ruby Hill property. 
 
   -- Strengthened Board with the appointment of Stephen Gottesfeld at the 
      annual general meeting, bringing nearly 30 years of global mining 
      experience in environmental, sustainability, legal and governance matters 
      across the mine lifecycle. 

UPCOMING CATALYSTS

Over the next 18 months, the Company is targeting the following key catalysts while continuing to identify opportunities to optimize the development schedule:

Archimedes Underground

   -- First gold mined -- Q4 2026 

Lone Tree Plant

   -- Commence construction -- Q4 2026 
 
   -- Completion of detailed engineering -- late Q1 2027 
 
   -- Filtration plant completion -- early Q4 2027 
 
   -- First gold pour -- Q4 2027 

Technical Studies

   -- Granite Creek underground (Feasibility) -- Q3 2026 
 
   -- Cove underground (Feasibility) -- Q3 2026 
 
   -- Archimedes Underground (Feasibility) -- approximately mid-2027 
 
   -- Mineral Point Open Pit) (Pre-Feasibility) -- approximately mid-2027 
 
   -- Granite Creek open pit (Pre-Feasibility) -- timing under review 

OUTLOOK

The Company remains on track to meet its 2026 guidance as originally published in its 2025 Year End Annual Report on Form 10-K on February 19, 2026 subject to the following:

Growth capital expenditures are expected to be largely in line with the $150 million to $175 million guidance.

   -- Lone Tree plant refurbishment capital expenditures are expected to be 
      lower in 2026 than guided, management was conservative in estimating 
      expenditures for Lone Tree during the recapitalization planning process 
      earlier in year to ensure that the Company raised sufficient capital. 
 
   -- Archimedes expenditures are expected to be higher reflecting a change in 
      strategy for long-term surface infrastructure. Based on positive drill 
      results, management is pivoting from refurbishment of certain existing 
      facilities on site to construction of a new worker change facility and 
      additional offices that are expected to improve operating effectiveness 
      both for Archimedes and Mineral Point. 
 
   -- Exploration expenses are expected to be approximately $10 million lower 
      in 2026 due to the personnel shortages at the Archimedes project and 
      drill rig availability as well as contractor personnel shortages at 
      Mineral Point project. 

This outlook, including expected results and targets, is subject to various risks, uncertainties and assumptions, which may impact future performance and the Company's ability to achieve the results and targets discussed in this section. Please refer to "Forward-Looking Information" section. The Company may, but is under no obligation to, update this outlook depending on changes in metal prices and other factors.

At the request of the copyright holder, you need to log in to view this content

Disclaimer: Investing carries risk. This is not financial advice. The above content should not be regarded as an offer, recommendation, or solicitation on acquiring or disposing of any financial products, any associated discussions, comments, or posts by author or other users should not be considered as such either. It is solely for general information purpose only, which does not consider your own investment objectives, financial situations or needs. TTM assumes no responsibility or warranty for the accuracy and completeness of the information, investors should do their own research and may seek professional advice before investing.

Comments

We need your insight to fill this gap
Leave a comment