HOUSTON, Aug. 12, 2026 (GLOBE NEWSWIRE) -- Fervo Energy Company ("Fervo" or the "Company") $(FRVO)$, the global pioneer of next-generation geothermal energy, today reported financial and operational results for the second quarter ended June 30, 2026.
"Fervo continues to demonstrate the power of enhanced geothermal at scale," said Tim Latimer, CEO and Co-founder of Fervo. "We believe that demand for firm, carbon-free power has never been stronger, and our commercial pipeline reflects that - we're converting our extensive resource portfolio into shovel-ready capacity quarter after quarter. Alongside that growth, commissioning at Cape Station Phase I, record-setting drilling at Phase II, and continued derisking of our pipeline all bring Fervo closer to the goal of making geothermal the world's cheapest, most reliable form of power." -------------------------------------------------------------
BUSINESS AND OPERATIONAL HIGHLIGHTS
-- Continued to see strong growth in power demand across all categories of
buyers, with behind-the-meter capabilities playing a growing role in
meeting that demand outside conventional grid interconnection timelines.
-- Raised its long-term development target to 1.1 gigawatts by 2030 - a
100-megawatt increase - as commercial and technical confidence in the
Company's pipeline continues to build.
-- Advanced Cape Station Phase I toward commercial operation, achieving
mechanical completion on GeoBlocks 1 and 2 and progressing commissioning,
with GeoBlock 3 mechanical completion expected in the coming months.
GeoBlock 1 first power is targeted for the fourth quarter of 2026, with
full production anticipated by year-end; GeoBlocks 2 and 3 are expected
to reach initial power in early 2027.
-- Set a new company drilling record with Sawtooth 7 - the ninth Fervo 3.0
well and most complex well design to date - reaching a measured depth of
nearly 19,500 feet in a 460degF resource with a spud-to-total-depth of
just 21 days.
-- Progressed Cape Station's second phase of development, with eight
GeoBlocks slated to come online in 2028, and added a third Helmerich &
Payne rig in line with the Phase II development plan.
-- Accelerated pipeline maturation, moving eight GeoBlocks (400 megawatts)
into Advanced Development while advancing 10.5 gigawatts of capacity
potential across two new GeoClusters into Early Development.
FINANCIAL HIGHLIGHTS
-- Marked its debut as a public company in the second quarter of 2026,
completing its IPO and raising approximately $2.2 billion in gross
proceeds.
-- Reported Q2 2026 operating loss of $28.7 million and net loss of $55.9
million.
-- Reported Q2 2026 capital expenditures of $226.5 million, compared to
$108.0 million in Q2 2025, reflecting continued investment in Cape
Station development and construction activities.
-- Expect total capital expenditures of approximately $850.0 to $900.0
million in the second half of 2026, in line with previously disclosed
expectations, reflecting continued construction activity at Cape Station
as well as broader pipeline development activities, including long-lead
procurement and appraisal work across the Company's GeoCluster portfolio.
BUSINESS UPDATES
Commercial
Fervo continues to see robust commercial demand for firm, carbon-free power, driven by the scale of AI and data center build-out, the re-shoring of domestic manufacturing, and broader electrification straining existing grid capacity. Buyers across categories -- utilities, industrial offtakers, and hyperscale data center developers -- continue to seek out Fervo's 24/7 geothermal power as a differentiated solution to that demand, and the Company's commercial pipeline reflects that momentum.
As part of its GeoCluster approach to AI data center development, Fervo is pursuing behind-the-meter delivery pathways in addition to conventional grid-delivered power purchase agreements - structures under which the Company delivers baseload power directly to a customer's on-site load, alongside ancillary energy systems developed by others, rather than through the grid. Fervo believes that behind-the-meter developments will serve as a critical bridge for customers that urgently need power sooner than the grid can provide, and that these developments will be connected to the grid over time.
Construction
Cape Station Phase I is an approximately 100-megawatt installation comprising three 33-megawatt GeoBlocks. Fervo has achieved mechanical completion on GeoBlocks 1 and 2, with mechanical completion of GeoBlock 3 expected over the coming months. Commissioning on GeoBlock 1 continued throughout the quarter with the first set of wells having been connected to the power plant, moving geothermal brine through the heat exchangers and spinning the turbines. Fervo expects to begin generating test power at GeoBlock 1 in the fourth quarter of 2026, with full production anticipated by year-end. GeoBlocks 2 and 3 are expected to follow a similar sequence, with initial power in early 2027 ramping to full power over the ensuing months.
Fervo's second phase of development at Cape Station, 400 megawatts across eight 50-megawatt GeoBlocks, continues to advance toward its 2028 delivery date, building on the lessons of Phase I. This expansion incorporates the Company's 3.0 well design, with longer laterals and larger-diameter casing than Phase I, engineered to increase power output per well while reducing installed cost per kilowatt. During the quarter, Fervo drilled Sawtooth 7, its ninth Fervo 3.0 well, reaching a measured depth of nearly 19,500 feet in a 460degF resource in just 21 days spud-to-total-depth, a new Company record for drilling pace on its most complex well design to date.
The drilling performance of the Sawtooth 7 well, combined with its design and resource temperature, underpins Fervo's confidence in its cost trajectory. Based on progress to date, Fervo continues to expect Phase II to achieve an all-in cost of $5,500 per kilowatt, a key step toward its long-term target of $3,000 per kilowatt.
Portfolio
Fervo's development pipeline, which totaled more than 50 gigawatts as of quarter-end, continued to advance during the second quarter. Approximately 400 megawatts moved from Early Development into Advanced Development, driven by progress at one of the Company's leading prospects, where Fervo completed geological surveys, secured appraisal permits, initiated origination activities, and submitted an interconnection queue application. Separately, two additional GeoClusters totaling 10.5 gigawatts of capacity potential entered Early Development, following newly completed heat-initially-in-place studies by independent engineering firm DeGolyer and MacNaughton. Fervo also anticipates beginning an appraisal drilling program in Q4 2026.
Fervo's current land portfolio spans over 650,000 acres.
Financing
In May 2026, Fervo completed its initial public offering (IPO) and listed on Nasdaq. The IPO was significantly upsized and priced well above the initial range, resulting in gross proceeds of approximately $2.2 billion, including the full exercise of the underwriters' over-allotment option. The IPO allows Fervo to accelerate its strategic priorities, as the Company prepares to place over a gigawatt of capacity online by the end of the decade.
Earlier in the quarter, Fervo repaid all outstanding borrowings under the loan agreements with XRL ALC, LLC (the "XRC Facility") using proceeds from the Project Granite Facility, the $421 million non-recourse project debt financing for the first phase of Cape Station that Fervo closed in Q1 2026, and the XRC Facility was terminated.
CONFERENCE CALL
Fervo will host a conference call to discuss its second quarter 2026 business, operational and financial highlights at 10:00 a.m. ET (9:00 a.m. CT) today, August 12, 2026. A live webcast of the conference call will be available in the "Events" section of the Company's investor relations website at ir.fervoenergy.com. A replay of the call will be available shortly after the live webcast's conclusion.
ABOUT FERVO
Fervo Energy (NASDAQ: FRVO) is a modern power company built around one of the market's most important needs: affordable, dependable new power supply. Through the large-scale deployment of enhanced geothermal systems, Fervo has established a repeatable, industrial approach to building utility-scale power. The Company is transforming geothermal into a clean, reliable, cost-competitive solution designed to meet rising demand from AI hyperscalers, utilities, and a more electricity-intensive economy. For more information, visit www.fervoenergy.com.
FORWARD-LOOKING STATEMENTS
This press release contains "forward-looking statements" within the meaning of Section 27A of the Securities Act and Section 21E of the Exchange Act, which involve risks, uncertainties, and assumptions. All statements, other than statements of historical fact, are forward-looking statements. When used in this press release, the words "aim," "anticipate," "believe," "continue," "could," "estimate," "expect, " "forecast," "future," "guidance," "intend," "may," "model," "outlook," "plan," "positioned," "potential," "predict," "project," "seek," "should, " "target," "will," "would," and similar expressions (including the negative of such terms) are intended to identify forward-looking statements, although not all forward-looking statements contain such identifying words. Although Fervo believes that the expectations and assumptions reflected in its forward-looking statements are reasonable as and when made, they involve risks and uncertainties that are difficult to predict and, in many cases, beyond Fervo's control. Accordingly, forward-looking statements are not guarantees of future performance, and Fervo's actual outcomes could differ