Bannerman Energy Says Early Works Construction Activities at Namibia Uranium Project on Schedule

MT Newswires Live09-29 08:04

Bannerman Energy (ASX:BMN) said early works construction activities at its Etango uranium project in Namibia continue to advance in line with overall budget and schedule expectations, according to a Tuesday filing with the Australian bourse.

With a contractor workforce of about 523 personnel on site, the bulk earthworks package is now almost complete, with phase four expected to be completed in December, per the filing.

Aggregate production of heap leach drainage has reached about 50% of the total requirement, while dry plant civil and mechanical design is about 98% complete, with all relevant mechanical packages ready for order placement upon a final investment decision the company is targeting during the fourth quarter.

Bannerman added that wet plant detailed concrete and structural engineering is approximately 33% complete, and phase one of the permanent water supply pipeline is roughly 90% complete.

Disclaimer: Investing carries risk. This is not financial advice. The above content should not be regarded as an offer, recommendation, or solicitation on acquiring or disposing of any financial products, any associated discussions, comments, or posts by author or other users should not be considered as such either. It is solely for general information purpose only, which does not consider your own investment objectives, financial situations or needs. TTM assumes no responsibility or warranty for the accuracy and completeness of the information, investors should do their own research and may seek professional advice before investing.