Press Release: Denison Reports Financial and Operational Results for Q3 2026, Highlighted by 24% Total Completion After First Quarter of Full-Scale Construction at Phoenix ISR Uranium Mine

Dow Jones11-05

TORONTO, Nov. 4, 2026 /PRNewswire/ -- Denison Mines Corp. ("Denison" or the "Company") (TSX: DML) (NYSE American: DNN) today filed its Condensed Consolidated Financial Statements and Management's Discussion & Analysis ("MD&A") for the three and nine months ended September 30, 2026. Both documents will be available on the Company's website (at www.denisonmines.com), SEDAR+ (at www.sedarplus.ca) and EDGAR (at www.sec.gov/edgar). The highlights provided below are derived from these documents and should be read in conjunction with them. All amounts in this release are in Canadian dollars unless otherwise stated. PDF version

David Cates, President and CEO of Denison commented, "With a relatively short timeline for construction of the Phoenix In-Situ Recovery ("ISR") uranium mine, executing during the prime summer construction season is critical. We are very pleased with our ability to immediately mobilize to site after regulatory approvals and ramp up activity to achieve a full-scale rate of construction for the third quarter. Denison's results showcase significant construction progress at Phoenix and the potential to add meaningful shareholder value from the discovery of new mineralization on site.

During the quarter, we prioritized schedule-critical and seasonally sensitive activities to capitalize on the summer construction season, and we ended our first quarter of full-scale construction with the project's total percentage completion estimated at 24%. Based on this initial progress, we continue to target completion of construction and achievement of first production during the second half of 2028, which is approximately 2 years after the commencement of full-scale construction.

By the end of October 2026, nearly 50% of all site civil work was complete, including the establishment of the main access road from Highway 914, and all scopes required to advance construction of the process plant, the delivery and installation of key electrical assets, the commencement of freeze well drilling, and preparation of the airstrip for operations in Q4. In addition, the schedule-critical concrete work required to start construction of the process plant building during the winter is substantially complete. Offsite fabrication of modularized equipment is also progressing, with key electrical infrastructure, the freeze plant, and certain process tanks, amongst other equipment and materials, already received on site or released for shipment to site.

We are also pleased to report encouraging exploration results at the emerging Phoenix North target area, which is located within the surface footprint of the Phoenix ISR mine site. Drill hole WR-857D1 intersected 0.39% eU(3) O(8) over 4.7 metres, and approximately 50 metres to the northeast drill hole WR-868 intersected 0.67% eU(3) O(8) over 2.5 metres. Drilling in this area continues into the fourth quarter, as the discovery of additional resources in the immediate vicinity of Phoenix could add significant value to the project."

Highlights

   -- Phoenix achieves 24% total completion after first quarter of full-scale 
      constructionBuilding on the successful completion of site preparation and 
      early works construction in early July, Denison made significant progress 
      executing on key construction work scopes during its first quarter of 
      full-scale construction on site.  The project's total percentage 
      completion as at September 30, 2026 is estimated at approximately 24%, 
      which includes (i) engineering, PCM, and owner's costs at 32% completion, 
      (ii) construction and construction indirect costs at 20% complete, and 
      (iii) fabrication and delivery of equipment and materials at 32% 
      complete.With full-scale construction commencing during the critical 
      summer construction season, initial construction activities have focused 
      on schedule and seasonally sensitive work.  Civil work continued with the 
      main site access road from Highway 914 currently available for use, the 
      substation area substantially completed and the freeze plant area and 
      airstrip significantly advanced (with 100% of the final grade completed 
      for the runway area). In addition, concrete work commenced in August and 
      continues into the fourth quarter of 2026.  By the end of October 2026, 
      site civil work is estimated to be nearly 50% complete and the concrete 
      work required to enable the commencement of construction of the process 
      plant building over the winter has been substantially completed. 
   -- Phoenix construction and procurement strategy allows continued 
      productivity during winter months With an approximately 2-year 
      construction timeline targeted for Phoenix, Denison developed a 
      procurement and execution strategy whereby key project components have 
      been procured directly by Denison, rather than through its contractors, 
      and modularization has been utilized wherever possible.  As a result, 
      Denison is responsible for making progress payments as equipment is 
      fabricated and the total project spend curve is thus front-loaded 
      relative to the rate of construction progress on site.  This approach 
      decouples fabrication of key equipment from onsite construction by 
      utilizing offsite fabrication facilities which allows for continued 
      productivity during the winter season.  Fabrication has commenced on the 
      majority of the process plant equipment and shipment release has occurred 
      for the site transformer, substation e-house, high-voltage substation 
      yard equipment, switchgear, generators, freeze plants, and certain 
      process tanks and construction bulks.  Year to date total Phoenix project 
      expenditures totaled $161.1 million, including $105.0 million on 
      construction and construction indirect costs and $39.0 million on 
      procurement of equipment and materials.  Life to date expenditures on 
      procurement of equipment and materials is approximately $56.8 
      million.Forecasted expenditures for 2026 are now estimated to be $278.6 
      million, with $39.9 million in procurement payments, $68.5 million in 
      construction and construction indirect costs, and $9.1 million in 
      engineering, PCM, and owner's costs estimated for the fourth quarter of 
      2026. 
   -- Additional mineralization discovered at Phoenix North exploration target 
      area, located within surface footprint of the Phoenix ISR mine 
      site During the third quarter of 2026, drill hole WR-857D1 intersected 
      0.39% eU3O8 over 4.7 metres from 409.9 metres to 414.6 metres at the 
      unconformity and represents the best mineralized hole drilled in this 
      area of sparse historic drilling.  WR-857D1 is located approximately 10 
      metres up-dip and along section of WR-857, which was completed during the 
      second quarter and intersected mineralized intervals of 0.20% eU3O8 over 
      1 metre from 417.6 metres, and 0.07% eU3O8 over 0.5 metres from 415.8 
      metres.  In October 2026, drill hole WR-868 encountered unconformity 
      associated mineralization (0.67% eU3O8 over 2.5 metres from 413.1 metres 
      to 415.6 metres) approximately 50 metres along strike to the northeast of 
      WR-857, and drill hole WR-869A intersected additional mineralization 
      (highlighted by 0.07% eU3O8 over 2.2 metres from 421.5 metres to 423.7 
      metres) 50 metres along strike to the southwest of WR-857.  See the MD&A 
      for further details. Taken together, mineralization has now been 
      intersected over 100-metres of strike length at the Phoenix North target 
      area, which remains open in multiple directions with the anticipated 
      optimal target horizon yet to be tested.While in the early stages of 
      exploration discovery, the results at Phoenix North are especially 
      encouraging as the mineralization is situated in the immediate vicinity 
      of the Phoenix ISR mine currently under construction. 

About Denison

Denison Mines Corp. was formed under the laws of Ontario and is a reporting issuer in all Canadian provinces and territories. Denison's common shares are listed on the Toronto Stock Exchange (the "TSX") under the symbol 'DML' and on the NYSE American exchange under the symbol 'DNN'.

Denison is a uranium mining, exploration and development company with interests focused in the Athabasca Basin region of northern Saskatchewan, Canada. The Company has an effective 95% interest in its flagship Wheeler River Uranium Project, which is the largest undeveloped uranium project in the infrastructure rich eastern portion of the Athabasca Basin region of northern Saskatchewan. In mid-2023, the Phoenix FS was completed for the Phoenix ISR mining operation, and an update to the 2018 Pre-Feasibility Study ("2018 PFS") was completed for the Gryphon deposit as a conventional underground mining operation (the "Gryphon Update"). Based on the respective studies, both deposits have the potential to be competitive with the lowest-cost uranium mining operations in the world.

Full-scale construction commenced at Phoenix in July 2026, which followed receipt of Federal approval of the project's Environmental Assessment and issuance of the Construction Licence in February 2026, as well as completion of site preparation and early works programs initiated in March 2026. Construction is expected to take approximately 2 years with first production targeted for the second half of 2028.

At the request of the copyright holder, you need to log in to view this content

Disclaimer: Investing carries risk. This is not financial advice. The above content should not be regarded as an offer, recommendation, or solicitation on acquiring or disposing of any financial products, any associated discussions, comments, or posts by author or other users should not be considered as such either. It is solely for general information purpose only, which does not consider your own investment objectives, financial situations or needs. TTM assumes no responsibility or warranty for the accuracy and completeness of the information, investors should do their own research and may seek professional advice before investing.

Comments

We need your insight to fill this gap
Leave a comment