Lithium Americas' Phase 1 Thacker Pass Lithium Project Construction on Track for Mechanical Completion in Late 2027

MT Newswires Live11-11

Lithium Americas' (LAC) phase 1 construction at its Thacker Pass lithium project in Nevada is on track for mechanical completion late 2027, with ramp-up to commercial production targeted in 2028, the company said Wednesday.

Capital cost estimate for Thacker Pass phase 1 increased to $3.83 billion, including contingency, from the previous estimated of $2.93 billion, Lithium Americas said. The company said it expects to fund the additional requirement from its contributions and loan reserve funding from the US Department of Energy.

At full capacity, Thacker Pass is expected to produce 40,000 tonnes per year of battery-quality lithium carbonate, according to Lithium Americas.

Disclaimer: Investing carries risk. This is not financial advice. The above content should not be regarded as an offer, recommendation, or solicitation on acquiring or disposing of any financial products, any associated discussions, comments, or posts by author or other users should not be considered as such either. It is solely for general information purpose only, which does not consider your own investment objectives, financial situations or needs. TTM assumes no responsibility or warranty for the accuracy and completeness of the information, investors should do their own research and may seek professional advice before investing.

Comments

We need your insight to fill this gap
Leave a comment