1206 ET - Lithium Americas' massive, nearly $900 million capital expenditure blowout at Thacker Pass Phase 1 will erode the project's net present value, according to TD Cowen's Craig Hutchison. In a report, the analyst notes that the 31% increase to $3.83 billion is "primarily driven by higher labour costs, installation requirements and staffing, with tariffs and logistics representing a smaller portion of the increase." He says this will weigh on project NPV at a time when lithium prices have weakened considerably over the last few months. The company also expects $100 million of incremental funding needs, bringing the total incremental funding requirement to $995 million. On the bright side, the contributions will increase the company's joint venture ownership percentage. Shares are down 8.1% to C$2.47.