Press Release: X-Energy Reports Third Quarter 2026 Results

Dow Jones11-12
   -- Revenues and grant income of $66.3 million, compared to revenues and 
      grant income of $30.4 million in 3Q 2025 
 
   -- Dow and X-energy receive Construction Permit from Nuclear Regulatory 
      Commission ("NRC") ahead of schedule 
 
   -- Selects Fluor Corporation ("Fluor") to advance nuclear engineering and 
      design for second Xe-100 project 
 
   -- Announced first procurement order with Alleima and Doosan Enerbility for 
      long-lead steam generator components 
 
   -- Announced Joint Development Agreement ("JDA") with American Electric 
      Power ("AEP") to advance feasibility work for a proposed 960 MW Xe-100 
      small modular reactor ("SMR") project in Indiana 
 
   -- Xe-100 SMR accepted into the United Kingdom's Generic Design Assessment 
      ("GDA") process 
 
   -- Vertical construction of TX-1 fuel fabrication facility complete, project 
      advances into the next phase which will include interior buildout, 
      equipment installation and construction of supporting facilities 
 
   -- Strong balance sheet with $1.8 billion in total liquidity, consisting of 
      $1.0 billion in cash and cash equivalents, $0.5 billion in short-term 
      investments and $0.3 billion in long-term investments, and zero debt 
      outstanding 

ROCKVILLE, Md., Nov. 12, 2026 (GLOBE NEWSWIRE) -- X-Energy, Inc. (Nasdaq: XE) ("X-energy" or the "Company"), a leading developer of advanced nuclear reactors and fuel technology, today announced third quarter 2026 financial results and operational highlights.

"Our third quarter results and recent project developments reflect meaningful progress in executing our strategy and advancing our technology toward commercial deployment. We are building momentum as we deepen relationships with leading energy and industrial companies and advance opportunities across our pipeline," said J. Clay Sell, CEO of X-energy. "The NRC recently issued the construction permit for Dow's Long Mott project in Texas and it was received over a month ahead of schedule. This marks the first construction permit issued by the NRC in the United States for an advanced nuclear project site designed to provide industrial process heat."

"Furthermore, we are excited to collaborate with AEP, a major investor-owned utility with extensive experience and expertise developing and operating critical energy infrastructure. This project in Indiana represents our second announced commercial deployment opportunity supported by Amazon and gives us greater visibility into our path toward deployment. During the quarter, we also completed the vertical construction of our TX-1 fuel fabrication facility, and the next phase includes interior buildout and equipment installation. In addition, the acceptance of our Xe-100 reactor into the United Kingdom's Generic Design Assessment process represents an important step toward advancing our opportunity in the U.K. with Centrica."

"We are in a differentiated position of strength, supported by our strong balance sheet and significant funding. Our regulatory progress marks a major milestone for our technology, while our growing commercial momentum bolsters our pipeline of reactors and demand for TRISO-X fuel," concluded Sell.

Operational Highlights

   -- NRC Issues Construction Permit for Dow's Long Mott Project: Dow and 
      X-energy announced that the NRC has approved the Construction Permit 
      Application ("CPA") for the proposed Long Mott Generating Station in 
      Seadrift, Texas ahead of schedule. The permit marks an important 
      milestone in the regulatory review process for the proposed advanced 
      nuclear project, which is being developed under the U.S. Department of 
      Energy's Advanced Reactor Demonstration Program ("ARDP"). The project is 
      intended to provide zero-carbon emissions electricity and 
      high-temperature steam to Dow's Seadrift Operations site, replacing 
      existing energy and steam assets near their end-of-life. The NRC's 
      approval follows a comprehensive review of the proposed facility, site 
      characteristics, construction plans, environmental considerations and 
      safety-related information submitted as part of the CPA process. Issuance 
      marks the first NRC CPA approval of a high-temperature gas-cooled reactor 
      ("HTGR") in nearly 60 years, the first-ever pebble-bed HTGR approval and 
      the first-ever for an advanced nuclear industrial deployment. 
 
   -- Selects Fluor for Design and Engineering Services: For Energy Northwest's 
      Cascade Advanced Energy Facility near Richland, Washington, Fluor will 
      provide engineering, design development, supply chain, estimating and 
      project controls services for the areas of the plant containing the 
      Xe-100 reactors and the systems that support them (the "nuclear island"). 
      The agreement between X-energy and Fluor represents their second 
      commercial contract for nuclear island engineering and design, building 
      on Fluor's ongoing work for the Company's first proposed Xe-100 project 
      in Texas under the ARDP. This enables X-energy and Fluor to incorporate 
      learnings from one project into the next, with the aim of targeting 
      long-term cost and schedule reductions through standardization and highly 
      repeatable project execution. 
 
   -- Executes First Order for Steam Generator Components: Announced the first 
      procurement order of steam generator tubing from Alleima and Doosan 
      Enerbility for the Company's Xe-100 advanced SMR. This follows the 
      signing of a strategic framework by the three companies earlier this year 
      as the Company scales its supply chain to meet its growing commercial 
      pipeline. Execution advances a safety-significant, long-lead component 
      for the first deployment of the Xe-100. Alleima will leverage its 
      expertise in high-temperature alloys to manufacture specialized steel 
      tubing, which Doosan will bend into helical coils using its proprietary 
      fabrication processes. These coils are a central component of the Xe-100 
      steam generator, safely removing heat to produce high-temperature steam 
      at up to 565degC, and allowing a single Xe-100 to deliver both 
      electricity and high-temperature process heat for industrial 
      applications. 
 
   -- Partners with AEP and Amazon: Announced a JDA with AEP to advance 
      feasibility work for a proposed 960 MW Xe-100 SMR project in Indiana. 
      Amazon will provide certain project development funding for the effort, 
      marking the second commercial deployment opportunity under X-energy and 
      Amazon's collaboration aimed to bring more than 5 GW of new nuclear 
      capacity to the U.S. grid by 2039. X-energy and AEP will evaluate the 
      development of a 12-unit Xe-100 plant in Sullivan County, Indiana. The 
      proposed project would redevelop the AEP-owned brownfield site for 
      advanced nuclear power, adding clean baseload capacity to help meet 
      growing demand for safe, reliable energy. 
 
   -- U.K. Regulators Begin Design Review for Xe-100: The U.K. Government has 
      directed regulators to accept the Xe-100 reactor for design review and 
      advance X-energy's and Centrica's efforts to deploy up to 6 GW of new 
      nuclear in the U.K. GDA acceptance formally triggers the process of 
      assessing the design's acceptability for deployment and operation ahead 
      of the technical and environmental evaluations required for site-specific 
      licensing and permitting. The assessment is expected to take 
      approximately three years and will be administered by the U.K. Office for 
      Nuclear Regulation, the Environment Agency, and Natural Resources Wales. 
      The submission builds on the Xe-100's U.S. licensing progress and is 
      expected to benefit from expanded collaboration between the U.K. 
      regulators and the U.S. NRC, enabling transfer of NRC-reviewed design 
      documentation and safety analyses into U.K. design reviews. 
 
   -- TX-1 Vertical Construction Complete, Advances to Next Phase: Vertical 
      construction for the shell of the Company's TX-1 fuel facility in Oak 
      Ridge, Tennessee was completed on schedule in the third quarter. The 
      project has advanced into its next phase of construction, which will 
      include interior buildout, installation of fuel fabrication equipment and 
      continued construction of supporting facilities. Once operational, TX-1 
      is expected to produce approximately 700,000 TRISO-X fuel pebbles 
      annually, equivalent to 5 metric tons of uranium ("MTU"), with capacity 
      to provide fuel for up to 11 Xe-100 reactors. The U.S. NRC granted 
      TRISO-X a 40-year Special Nuclear Material License covering the facility 
      earlier this year, the first-ever NRC Category 2 fuel fabrication license 
      issued for the processing of high-assay low-enriched uranium. TX-1 is 
      expected to be the first new commercial-scale advanced U.S. nuclear fuel 
      fabrication facility built in more than 50 years. 

Financial Results

 
                           Three Months 
                         Ended September                  Nine Months Ended 
                               30,                          September 30, 
                         ----------------                 ----------------- 
(Dollars in millions)     2026     2025     % Change        2026      2025    % Change 
----------------------   ------   -------   --------      --------   ------   -------- 
Total revenues and 
 grant income            $ 66.3   $  30.4        118%     $  164.4   $ 72.7        126% 
Total operating 
 expenses                 169.9      71.1        139%        444.1    182.5        143% 
Net cash used in 
 operating activities     (51.2)    (30.8)        66%       (215.8)   (92.7)       133% 
Net cash used in 
 investing activities     (49.9)    (23.1)       116%       (289.5)   (41.8)       593% 
Net cash provided by 
 (used in) financing 
 activities                (0.1)     (0.2)       (45)%     1,091.1     50.2      2,072% 
 
 

Total revenues and grant income in the three months ended September 30, 2026 were $66.3 million, including $51.5 million of services revenue and $14.8 million of grant income. Total revenues and grant income in the nine months ended September 30, 2026 were $164.4 million, including $141.6 million of services revenue and $22.8 million of grant income. Total revenues and grant income increased 118% and 126% for the three and nine months ended September 30, 2026, respectively, compared to the comparable prior-year period. This was primarily due to increases of $29.3 million and $85.0 million in revenue and grant income from the ARDP Agreement with the DOE for the three and nine months ended September 30, 2026, respectively. This was driven by an increase in project execution activities under the ARDP Agreement as the Company continued to advance the development and finalization of the Xe-100 reactor design. The increase reflected higher spending on materials, subcontractor services, and compensation costs to support the expanded scope of work.

Total operating expenses in the three months ended September 30, 2026 were $169.9 million, including $93.6 million of Direct costs. Total operating expenses in the nine months ended September 30, 2026 were $444.1 million, including $245.6 million of Direct costs. Total operating expenses increased 139% and 143% for the three and nine months ended September 30, 2026, respectively, compared to the comparable prior-year periods. This was primarily due to increases of $54.7 million and $141.9 million in Direct costs and increases of $43.9 million and $120.4 million in Selling, general, and administrative expenses for the three and nine months ended September 30, 2026, respectively, compared to the comparable prior-year periods.

The increase in Direct costs was primarily driven by expanded activity under the ARDP Agreement. Subcontracting costs increased by $23.5 million and $52.8 million for the three and nine months ended September 30, 2026, respectively. Direct materials costs increased $15.6 million and $33.3 million for the three and nine months ended September 30, 2026, respectively. Additionally, compensation costs increased by $15.3 million and $53.0 million for the three and nine months ended September 30, 2026, respectively, including $10.9 million and $42.0 million from higher employee headcount to support the expanded activity under the ARDP Agreement, and $4.4 million and $11.0 million from increased non-cash equity-based and unit-based compensation expense for the three and nine months ended September 30, 2026 due to equity grants to certain former holders of Profits Interest Units ("PIUs") in connection with the Company's IPO in April.

The increase in Selling, general, and administrative expenses was driven by an increase in non-cash equity-based and unit-based compensation expense of $18.4 million and $49.2 million for the three and nine months ended September 30, 2026, respectively, due to the equity grant to certain PIU holders discussed above. Compensation costs increased a further $9.0 million and $29.4 million for the three and nine months ended September 30, 2026, respectively, primarily due to higher employee headcount. Additionally, infrastructure and professional service costs increased by $8.0 million and $23.8 million for the three and nine months ended September 30, 2026, respectively. Selling, general and administrative expenses increased a further $8.5 million and $12.0 million for the three and nine months ended September 30, 2026, respectively, from contractor costs related to corporate projects, including design costs for TX-2.

Net cash used in operating activities in the nine months ended September 30, 2026 was $215.8 million of net cash compared to $92.7 million for the nine months ended September 30, 2025. The increase in cash used in operating activities is primarily driven by increases in activity on the ARDP Agreement, deposits to vendors for long-lead materials, and corporate headcount and corporate contractors during the nine months ended September 30, 2026 compared to the nine months ended September 30, 2025.

Net cash used in investing activities in the nine months ended September 30, 2026 was $289.5 million of net cash compared to $41.8 million for the nine months ended September 30, 2025. The increase in net cash used in investing activities was attributable to investments in held-to-maturity securities and capital expenditures. During the nine months ended September 30, 2026, we purchased investments of $425.3 million, which were offset by proceeds from investment maturities of $233.9 million. There was no investment activity during the nine months ended September 30, 2025. During the nine months ended September 30, 2026, compared to the corresponding prior year period, we had a $98.8 million increase in capital expenditures related to the construction of facilities, which was offset by a $42.5 million increase in reimbursements received for the capital expenditures qualifying under government grant programs.

Net cash provided by financing activities in the nine months ended September 30, 2026 was $1.1 billion of net cash compared to $50.2 million for the nine months ended September 30, 2025. The net cash provided by financing activities during the nine months ended September 30, 2026 was primarily due to $1.1 billion of net proceeds from X-energy's initial public offering. The net cash provided by financing activities during the nine months ended September 30, 2025 was primarily due to the January 2025 issuance of Series C-1 preferred units of $53.4 million, offset by $2.5 million of cash paid for associated issuance costs.

Liquidity

 
                         September 30,  December 31, 
(Dollars in millions)        2026           2025      % Change 
----------------------   -------------  ------------  -------- 
Cash and cash 
 equivalents              $    1,044.1   $     458.9       127% 
Short-term investments           514.3         304.9        69% 
Long-term investments            247.1         261.5        (5)% 
                             ---------      -------- 
Total liquidity           $    1,805.5   $   1,025.3        76% 
                             =========      ======== 
 
 

Cash and cash equivalents totaled $1.0 billion as of September 30, 2026. Short-term investments totaled $514.3 million and Long-term investments totaled $247.1 million, for total liquidity of $1,805.5 million as of September 30, 2026. The Company had no debt outstanding as of September 30, 2026 and December 31, 2025.

Project Pipeline

The Company's expected project pipeline consists of 144 reactors with three announced commercial Xe-100 projects in the U.S. and the fourth announced in the U.K. for approximately 11.5 gigawatts electric, assuming each customer exercises its contingent rights in full. X-energy has high-quality customers and partners across its four existing projects with Dow, Amazon/Energy Northwest, Centrica and Amazon/American Electric Power, who are expected to underpin the deployment of the initial fleet of Xe-100 reactors.

Participation in Upcoming Investor Conferences

X-energy is scheduled to participate in the following upcoming events:

   -- UBS Global Technology and AI Conference, November 30, 2026, Scottsdale, 
      AZ 
 
   -- Truist Virtual Nuclear Summit, December 10, 2026 (virtual) 
 
   -- Stifel Frontier Tech 2.0 Energy Summit, December 10, 2026, New York, NY 
 
   -- Jefferies Power, Energy, Utilities, Clean & Pipes Conference, March 2, 
      2027, New York, NY 

Conference Call

X-energy will host a conference call today at 8:00 a.m. ET to discuss these results. A live audio webcast of the conference call can be accessed on the "Events & Presentations" section of the Investor Relations page of the Company's website by visiting https://investors.x-energy.com, along with the Company's presentation materials. A replay of the webcast will be available on the website for at least one year following the event.

About X-energy

X-energy is a leading designer of advanced small modular nuclear reactors ("SMR") and fuel technology developed to establish a new standard in clean, safe, reliable energy. X-energy's intrinsically safer Xe-100 high-temperature gas-cooled reactor and TRISO-X particle fuel expand applications for nuclear technology, with commercial projects across grid, industrial, and AI. Together, X-energy's technology drives enhanced safety, lower cost, faster construction timelines, and scalable deployment when compared with other SMRs and conventional nuclear. For more information, visit X-energy.com or connect with us on X or LinkedIn.

Contacts

Investor Relations

Patricia Gil

+1 301.558.3040

investors@x-energy.com

Media

Robert McEntyre

+1 240.673.6565

media@x-energy.com

Forward-Looking Statements

This press release contains forward-looking statements within the meaning of the Private Securities Litigation Reform Act of 1995. X-energy intends such forward-looking statements to be covered by the safe harbor provisions for forward-looking statements contained in Section 27A of the Securities Act of 1933, as amended (the "Securities Act"), and Section 21E of the Securities Exchange Act of 1934, as amended. Such statements can be identified by the fact they do not relate strictly to historical or current facts. Words such as "anticipate," "assume," "believe," "continue," "could," "designed to," "estimate," "expect," "intend," "may," "plan," "potential," "predict," "project," "future," "will," "would," "seek," "should," "foreseeable," the negative version of these words, or similar terms and phrases may identify forward-looking statements, but the absence of these words does not mean that a statement is not forward-looking. These forward-looking statements include, but are not limited to, statements relating to the Company's strategic and operational plans, including plans and expected timing, completion, capacity and benefits with respect to its fuel fabrication campus; expectations with respect to changes in ARDP; the Company's ability to receive regulatory approvals and on accelerated timeframes; expected project deployment sizes, siting, timelines, benefits and related funding; the Company's expected project pipeline and exercise by customers of their contingent rights; the Company's funding, liquidity and capital resources in relation to its future plans; the Company's ability to build momentum; the expected duration and outcome of the U.K. Generic Design Assessment and expected benefits from collaboration with the NRC; the Company's ability to continue to execute its business plan and achieve Nth-of-a-kind deployment efficiencies; its ability to continue to reduce the risk of X-energy's supply chain; expectations regarding future supply of key nuclear supplies (including graphite, tubing and HALEU) from its suppliers; the success of the Company's supply chain partnerships, future growth, and business outlook.

These forward-looking statements are neither promises nor guarantees and are subject to a number of risks, uncertainties, and assumptions. Actual results may differ materially as a result of a number of factors, including, without limitation, the Company's ability to achieve final investment decisions from its customers; ability to realize its plans to deliver a commercial Xe-100; the Company's projects may be subject to delays or setbacks, increasing costs or termination; the risk that customers do not exercise their contingent rights in full; its liquidity and ability to raise capital; changes or delays in support from the U.S. government, including ARDP and expected modification; changes, delays, or an inability to receive licenses or other governmental approvals necessary for X-energy's reactors and fuel facilities; uncertainty and changes in expected costs, schedules and unit economics due to inflation; supply chain constraints (including access to HALEU, tubing, graphite and certain other materials), including suppliers inability to fulfill their contractual obligations; the Company's minimum purchase and prepayment commitments; reliance on a limited number of specialized suppliers and exposure to supply disruptions, quality issues, and trade policy changes; labor availability, site-specific factors and first-of-a-kind risks; X-energy's limited operating experience at intended scale and the possibility that latent design or operational issues may emerge; safety, security, and cybersecurity incidents; the nascent and uncertain market adoption of SMRs and the possibility that demand may grow more slowly than expected or customers may defer or cancel projects; competition from competitors with potentially greater resources or lower costs; reliance on key partners and customers, including Amazon's support on multiple projects, and the risk that changes in partner or customer priorities or timelines could materially affect commercialization; customer contractual terms that may constrain capacity allocation and compress margins; licensing and scaling X-energy's fuel fabrication campus and delays in licensing or facility construction; general economic conditions; changes in laws, regulations, incentives, energy market rules, export controls, or government policies; shifts in public perception and political support for nuclear energy or Company customers; dependence on key personnel and ability to hire and retain talent; and ability to obtain, maintain, or enforce IP rights. The foregoing list of factors is not exhaustive. Additional information concerning these and other factors can be found in the section entitled "Risk Factors" in X-energy's most recent Form 10-Q filed with Securities and Exchange Commission ("SEC"), and in subsequent filings made with the SEC.

Caution must be exercised in relying on these and other forward-looking statements. Due to known and unknown risks, X-energy's results may differ materially from its expectations and projections. Any forward-looking statements made herein speak only as of the date of this press release, and you should not rely on forward-looking statements as predictions of future events. Although X-energy believes that the expectations reflected in the forward-looking statements are reasonable, it cannot guarantee that the future results, performance or achievements reflected in the forward-looking statements will be achieved or will occur. Except as required by law, X-energy does not undertake any obligation to update or revise any forward-looking statement, whether as a result of new information, future events or otherwise.

Non-GAAP Financial Measures

This press release presents information about certain non-GAAP financial measures. The non-GAAP financial measures are supplemental measures, are not defined by or presented in accordance with GAAP, have limitations as analytical tools, and should not be considered in isolation or as a substitute for analysis of X-energy's financial results as reported under GAAP. A potential limitation of these non-GAAP financial measures is that other companies may report similar non-GAAP metrics, but calculate them differently, which reduces the usefulness of these non-GAAP metrics as a comparative measure. Because of this and other limitations, you should not consider the non-GAAP financial measures as a substitute for GAAP-based financial performance measures. Reconciliations of these non-GAAP financial measures to the most directly comparable GAAP financial measures are provided herein.

 
 
                             X-ENERGY, INC. 
                  CONDENSED CONSOLIDATED BALANCE SHEETS 
               (in thousands, except unit and share data) 
                               (unaudited) 
 
                            September 30, 2026     December 31, 2025 
                           --------------------   ------------------- 
ASSETS 
Current assets 
Cash and cash equivalents   $         1,044,054    $          458,932 
Short-term investments                  514,348               304,908 
Accounts receivable                      51,407                32,940 
Unbilled receivables and 
 contract assets                         86,138                41,529 
Prepaid and other current 
 assets                                  23,722                11,491 
Due from related parties                 22,607                 4,580 
                               ----------------       --------------- 
Total current assets                  1,742,276               854,380 
                               ----------------       --------------- 
Long-term investments                   247,113               261,458 
Restricted cash                           4,403                 3,698 
Property and equipment, 
 net                                    148,719                50,105 
Operating lease 
 right-of-use assets                     21,308                22,696 
Other long-term assets                   55,696                18,934 
                               ----------------       --------------- 
Total assets                $         2,219,515    $        1,211,271 
                               ================       =============== 
LIABILITIES, MEZZANINE 
EQUITY, AND 
STOCKHOLDERS' EQUITY AND 
MEMBERS' DEFICIT 
Current liabilities 
Accounts payable            $             1,703    $            3,363 
Accrued liabilities                     123,382                51,217 
Due to related parties                    6,139                 4,225 
                               ----------------       --------------- 
Total current liabilities               131,224                58,805 
                               ----------------       --------------- 
Long-term deferred 
 revenue                                 12,800                12,800 
Long-term deferred 
 revenue with related 
 parties                                 13,333                 2,353 
Long-term operating lease 
 liabilities                             24,255                20,887 
Warrant liabilities                          --               274,166 
                               ----------------       --------------- 
Total liabilities                       181,612               369,011 
                               ----------------       --------------- 
Mezzanine equity 
Class A and B common 
 units(1)                                    --                95,153 
Series A, A-1, B, C, C-1, 
 and D redeemable 
 convertible preferred 
 units(1)                                    --             1,971,402 
Total mezzanine equity                       --             2,066,555 
                               ----------------       --------------- 
Preferred stock: $0.0001 
par value per share; 
10.0 million shares 
authorized, no shares 
issued and outstanding 
as of September 30, 
2026; no shares 
authorized, issued, and 
outstanding as of 
December 31, 2025                            --                    -- 

At the request of the copyright holder, you need to log in to view this content

Disclaimer: Investing carries risk. This is not financial advice. The above content should not be regarded as an offer, recommendation, or solicitation on acquiring or disposing of any financial products, any associated discussions, comments, or posts by author or other users should not be considered as such either. It is solely for general information purpose only, which does not consider your own investment objectives, financial situations or needs. TTM assumes no responsibility or warranty for the accuracy and completeness of the information, investors should do their own research and may seek professional advice before investing.

Comments

We need your insight to fill this gap
Leave a comment