Facing Backlash on Land, Data Centers Look to the Sea

Dow Jones11-15

Data centers on land have attracted a lot of opposition. So in response, more companies have an alternative: What if data centers were placed on the ocean, or on some other body of water, instead?

The idea is still in the early stages. But as battles over where to build data centers intensify, developers are betting that offshore facilities could face less opposition from the public. They wouldn't be located in neighborhoods, and many of the proposed projects plan to generate electricity from waves or tidal power and use seawater for cooling, which could help alleviate fears about power and water consumption.

Whether those advantages can outweigh the challenges of running computers at sea is an open question. But that hasn't stopped announcements of new ocean data-center projects from piling up.

In May, Portland, Ore.-based Panthalassa, a startup backed by investors including Peter Thiel, raised $140 million to build giant steel structures, each 278 feet long, that would power artificial-intelligence computing with electricity generated from waves, while floating untethered in the Pacific Ocean.

In July, Scottish firm Mocean Energy announced plans to put AI servers on floats far out at sea, powered by waves and solar panels, cooled by the surrounding water and linked to shore by satellite.

And in October, Ocean Power Technologies of New Jersey and Stratum Holdings of Florida signed a nonbinding letter of intent to test whether Ocean Power's prototype buoys, powered mainly by waves, wind and solar, could run Stratum's AI infrastructure without a power cable to shore.

Other developers have different approaches. Massachusetts-based DeepGreen Holdings has applied for a federal permit to study putting a tidal-powered underwater data center on the seabed off Eastport, Maine, and filed a similar application for Alaska's Cook Inlet. Tidal power comes from the flow of water close to shore as tides rise and fall.

And Japan's Mitsui O.S.K. Lines says it wants to build a new vessel or convert an existing ship into a floating data center moored in a port, powered either from shore or by a separate power ship.

Early stages

Most of the projects are still in the early stages.

Panthalassa says it plans to test its next-generation data center later this year and begin commercial deployment in 2027. DeepGreen is still vetting turbine and equipment partners and hasn't put anything in the water yet, says Louis Wolfson, the company's managing member. And Mitsui O.S.K. Lines is weighing sites for its first ship-based data center, according to Shinichi Ogawa, who leads the effort.

Mocean, meanwhile, completed a 13-month test of its wave-powered energy system in the spring of 2024. It announced plans in July to put AI servers on the unit and is now seeking funds for a demonstration.

The company's prototype is based on wave-energy technology it has been working on for a decade to provide electricity to offshore oil-and-gas operators. It consists of a floating device that moves with the waves, with a generator driven directly by that motion and few parts to break, says Cameron McNatt, the company's co-founder and chief executive. The system was able to generate electricity from waves up to 40 feet during testing, McNatt says, adding that very small waves produced less power.

Mocean intends for each unit, or node, to deliver about 500 kilowatts of power to AI computers through a combination of wave power and solar panels. In the test, the unit produced about 10 kilowatts, the company says. Mocean envisions nodes being joined into groups that could supply up to 100 megawatts and be placed where waves run strong, such as Western Europe, the U.S. West Coast, Chile and Western Australia. McNatt says the goal is to reach a gigawatt of capacity in five years and 10 gigawatts in a decade.

On calm, cloudy days, batteries would provide backup power. From shore, the units would be nearly out of sight.

"They're really low profile, sitting close to the water," McNatt says. "They would basically be invisible."

Challenges at sea

Generating electricity is one of the biggest challenges floating data centers face at sea.Running subsea cables back to shore to transmit power could eat up a project's budget before a developer even has a chance to prove its concept works, says Bryson Robertson, director of the Institute for Integrated Energy Systems at the University of Victoria. That is why many of the recently announced floating-data-center projects seek to generate power on site.

Machines that drift freely, rather than being anchored to the seabed, avoid the cost of moorings but face a different problem. Storms can drag them away from their intended locations, and steering them back takes power that otherwise could run the computers, according to Robertson.

Seawater itself is a problem because the salt can corrode metal. "You put anything into seawater, and it starts failing immediately," says Michael Barnard, a climate-technology consultant.

Barnacles, minerals and microorganisms built up on submerged surfaces, clogging intake filters and coating the heat exchangers that cool the servers, Barnard says. Sending crews out to fix equipment add cost and complexity. He questions whether wave machines could be kept running reliably enough for the job.

Mocean says it plans to use marine-grade anti-corrosion paint and antifouling paint, a coating designed to stop marine life from attaching to vessels, when needed. And it will tow units back to a dock for scheduled repairs.

Wave-energy devices, meanwhile, cannot simply be built bigger to generate more power, says Robertson. They have to be tuned to the rhythm of the waves where they operate. A device that grows too large wouldn't be able to capture much of what the ocean actually produces. "It's like building a 500-meter-wide wind turbine, but there's never enough wind to make it spin," he says.

Then there are the environmental concerns. In Maine, groups opposing DeepGreen's plan say the Bay of Fundy is habitat for some of the world's most endangered whales. Moving data centers farther offshore isn't the answer because it would add boat traffic that raises the risk of whale strikes, along with noise that can interfere with how whales find food and mates, says Kristen Monsell, oceans program litigation director at the Center for Biological Diversity, which has filed to take part in the federal review. She also pointed to water pollution and heat.

DeepGreen's Wolfson says the purpose of the multiyear preliminary study is to examine such concerns, adding that the company is only reviewing turbine systems that operate within safe acoustic limits for marine mammals and fish. He also says DeepGreen plans to consult tribal leaders, fishermen and town officials before seeking a license.

Wave-energy projects aren't new and companies involved in this space have faced a high rate of failure over the years for a variety of reasons, including the harsh ocean environment and high costs.

Still, Robertson says deep-pocketed technology companies might finally give them the room to keep trying. "It's nice to see industries start to spend money in the wave-energy space," he says. "No technology works the first time."

Write to reports@wsj.com

 

At the request of the copyright holder, you need to log in to view this content

Disclaimer: Investing carries risk. This is not financial advice. The above content should not be regarded as an offer, recommendation, or solicitation on acquiring or disposing of any financial products, any associated discussions, comments, or posts by author or other users should not be considered as such either. It is solely for general information purpose only, which does not consider your own investment objectives, financial situations or needs. TTM assumes no responsibility or warranty for the accuracy and completeness of the information, investors should do their own research and may seek professional advice before investing.

Comments

We need your insight to fill this gap
Leave a comment