SpaceX's (SPCX) proposed data center in Cochise County, Arizona, should not be approved until state and federal agencies complete their reviews, Attorney General Kris Mayes said in a letter to the county's Planning and Zoning Commission Thursday.
Mayes urged the commission to postpone its Dec. 9 vote on the special use permit, citing unresolved questions about the project's effect on the electric grid, water resources, public safety, traffic, wildlife and national security, her office said.
The campus could ultimately consume up to 6 gigawatts of electricity, nearly 20% of Arizona's power-generating capacity, according to the letter.
If the commission proceeds, Mayes recommended conditioning any approval on receipt of all required state and federal authorizations and barring piecemeal phased approvals, the letter said.
Mayes will host a public town hall in Cochise County on Dec. 3 and will seek additional information from SpaceX, her office said.
SpaceX did not immediately respond to a request for comment from MT Newswires.