Press Release: Orvana Announces Fy2026 Results & Fy2027 Guidance

Dow Jones08:30

TSX:ORV

TORONTO, Nov. 25, 2026 /PRNewswire/ -- Orvana Minerals Corp. (TSX: ORV) (OTCQX: ORVMF) (the "Company" or "Orvana") reports its results for fiscal year 2026 ("FY2026"), ended September 30, 2026, provides fiscal year 2027 ("FY2027") guidance for its Spanish and Bolivian subsidiaries, Orovalle Minerals, S.L. ("Orovalle") and Empresa Minera Paitití, S.A. ("EMIPA"), and provides an update on the ramp-up of its Bolivian subsidiary.

Juan Gavidia, CEO of Orvana commented:

"I am pleased to report that Orvana's fiscal 2026 delivered the building blocks of our long-term strategy on several fronts: $84 million EBITDA out of strong operational performance in Spain, where gold production exceeded the upper end of guidance; start-up of our ADR & SX-EW metallurgical plant in Bolivia, now ramping up toward 100% design throughput; and setting up our largest and most comprehensive exploration season to date at Taguas, Argentina.

We enter fiscal 2027 with both our Spanish and Bolivian operations in production, thus marking an important milestone for Orvana. Present focus is on delivering consistent operational performance and strengthening free cash flow across both operations. At the same time, we are excited to advance the next phase of exploration at Taguas, with simultaneous infill and exploration drilling programs during the summer season, expected to commence in the coming weeks."

Selected Annual Information

 
                                                   Years Ended September 30 
------------------                                 -------------------------- 
                                                            2026         2025 
-------------------------------------------------  -------------  ----------- 
GEO(1)                                                    45,506       35,705 
-------------------------------------------------  -------------  ----------- 
Consolidated Financial Performance (in 000's) 
   Revenue                                            $  182,038    $  98,903 
   Mining costs                                           90,173       63,833 
   Income (loss) before income taxes                      49,301      (7,796) 
   Comprehensive income (loss)                            33,576      (9,090) 
   EBITDA(1)                                              84,361       21,366 
   Cash provided by operating activities                  57,054       16,827 
   Capital expenditures (cash basis)                      56,031       33,163 
   Cash provided by financing activities                  10,082       32,634 
   Effect of exchange rate changes on cash                  (71)     (18,363) 
   Ending cash and cash equivalents                       42,048       28,253 
   Total assets                                          276,393      165,191 
   Current liabilities                                   120,308       42,390 
   Non-current liabilities                                76,608       77,472 
-------------------------------------------------  -------------  ----------- 
 COC(1) ($/oz)                                             1,843        1,847 
 ------------------------------------------------  -------------  ----------- 
Orovalle            AISC(1) ($/oz)                         2,229        2,186 
------------------  -----------------------------  -------------  ----------- 
 

Highlights

Spain:

   -- In FY2026, Orovalle produced 37,775 gold ounces, above the upper end of 
      its FY2026 guidance range of 34,000 to 37,000 ounces and up 29% year over 
      year, primarily driven by 16% higher tonnes milled and a 12% increase in 
      head grade. 
 
   -- Copper production of 2.9 million pounds in FY2026 was within the guidance 
      range of 2.7 to 3.0 million pounds and down 20% year over year, primarily 
      due to a 24% lower head grade and 10% lower recoveries, partially offset 
      by 16% higher tonnes milled. 
 
   -- FY2026 capital expenditures were $15.7 million (accrual basis), including 
      $11.0 million of sustaining capital, below the FY2026 sustaining capital 
      guidance range of $15.0 million to $17.0 million, primarily due to the 
      timing of projects at El Valle's tailings storage facility. 
 
   -- Total COC(1) (by-product) of $1,843 and AISC(1) (by-product) of $2,229 
      per ounce of gold sold for fiscal 2026 were below the guidance ranges of 
      $2,300 - $2,500 and $2,700 - $3,000, respectively. 
 
   -- Orovalle advanced its drilling program, completing 13,369 metres at the 
      El Valle and Carlés mines and an additional 1,427 metres of 
      greenfield drilling at the Lidia Project. 
 
   -- For fiscal 2027, Orovalle's operating strategy is based on the mineral 
      reserve set out in its Life of Mine Plan, as disclosed in the latest 
      Annual Information Form (December 2025, available on SEDAR+ and the 
      Company's website). The strategy remains focused on oxide ore at 
      Boinás and skarn ore at Carlés. 
 
   -- At Boinás, the focus remains on increasing drift-and-fill 
      development metres to provide access to additional oxide mining faces and 
      support oxide ore production. At Carlés, mined tonnage is expected 
      to remain broadly in line with fiscal 2026 levels, while jumbo 
      development activity is planned to increase compared with the prior year, 
      with the objective of providing access to deeper mining levels and 
      supporting ore availability for fiscal 2028. 
 
   -- Fiscal 2027 throughput is estimated at 475 kt, compared with 519 kt in 
      fiscal 2026. The lower expected throughput primarily reflects reduced 
      Boinás skarn ore availability, which is not expected to be offset by 
      increased Carlés skarn production in fiscal 2027, as mining activity 
      at Carlés will prioritize the development required to access deeper 
      levels. This development is expected to support increased ore 
      availability in fiscal 2028 and the potential extension of mine life. 
      These factors are reflected in the metal production guidance for fiscal 
      2027 compared with actual fiscal 2026 production. 

Bolivia:

   -- During fiscal 2026, EMIPA advanced its Oxide Stockpile Project ("OSP") 
      and commenced processing oxide ore through the expanded Don Mario 
      metallurgical plant. Production during the year included sulphide ore 
      processed through the gold and silver circuits in the first half of the 
      year as part of plant testing and commissioning activities and, beginning 
      in the fourth quarter, oxide ore processed through the ramp-up phase of 
      the OSP. 
 
   -- In total, EMIPA produced 1,597 ounces of gold, 14,680 ounces of silver 
      and 411,274 pounds of copper in FY2026. 
 
   -- As of the date of this news release, all Don Mario circuits required to 
      process its oxide ore stockpile are operational. Metallurgical 
      performance to date is generally in line with design assumptions, and the 
      plant is operating at approximately 1,300 tonnes per day. The ramp-up is 
      progressing in a controlled manner toward the plant's design capacity of 
      approximately 1,700 tonnes per day, targeted by the end of December 2026. 
 
   -- EMIPA Bonds I and II (as more fully described in the Company's most 
      recently filed audited financial statements available on www.sedarplus.ca 
      and www.orvana.com): 
 
          -- Bonds I matured on November 7, 2026 and were fully repaid 
             accordingly. EMIPA is completing the formalities required to 
             release the security over certain fixed assets. 
 
          -- The financial covenant ratios applicable to EMIPA's bonds were 
             outside the required thresholds as at June 30 and September 30, 
             2026. EMIPA is therefore currently within the cure period under 
             the terms of the bonds (the "Cure Period"), which runs through 
             December 8, 2026 and may be extended subject to bondholder 
             approval. 
 
          -- Following the full repayment of Bonds I, the Cure Period applies 
             only to Bonds II, which mature in February 2027 and are presented 
             as a current liability on the Company's balance sheet as at 
             September 30, 2026. The quarter ending December 31, 2026 is the 
             only remaining covenant testing period prior to maturity. 
 
          -- A meeting of the Bonds II bondholders is scheduled for November 
             30, 2026 to consider potential measures to address the covenant 
             situation, which could include, among other alternatives, 
             amendments, waivers and/or an extension of the Cure Period. Any 
             such measures would be subject to bondholder approval, and there 
             can be no assurance that the required approvals will be obtained. 

Argentina:

   -- The Company continues to evaluate the broader exploration potential of 
      the Taguas Project beyond the near-surface oxidized gold-silver resource 
      outlined in the 2021 Preliminary Economic Assessment (available on SEDAR+ 
      and the Company's website). The exploration strategy is focused on 
      advancing the existing oxide resource (full infill drilling on inferred 
      resources) while also evaluating the underlying sulphide mineralization 
      and the potential for a deeper porphyry-style copper-gold system. 
 
   -- During FY2026, the Company advanced this strategy through updated 
      geological modelling, Magnetotelluric and Induced Polarization 
      geophysical surveys, and its first deep drilling campaign, comprising two 
      holes totalling 2,173.7 metres. The Company also acquired the adjacent 
      Evelina Property, increasing the Taguas Project exploration footprint 
      from 3,274 to 7,289 hectares. 
 
   -- Results from the deep drilling campaign and related technical studies 
      support continued evaluation of the mineralized system at depth and its 

At the request of the copyright holder, you need to log in to view this content

Disclaimer: Investing carries risk. This is not financial advice. The above content should not be regarded as an offer, recommendation, or solicitation on acquiring or disposing of any financial products, any associated discussions, comments, or posts by author or other users should not be considered as such either. It is solely for general information purpose only, which does not consider your own investment objectives, financial situations or needs. TTM assumes no responsibility or warranty for the accuracy and completeness of the information, investors should do their own research and may seek professional advice before investing.

Comments

We need your insight to fill this gap
Leave a comment